4 Perform hydrostatic pressure test

Prepare boiler and test:

1.See pages 28 and 29 for tapping locations. Install:

a.Boiler drain (not furnished).

b.Water pressure gauge — for test only. Be sure gauge can handle test pressure — see step 3.

c.Air vent in upper tapping (K).

2.Plug remaining tappings.

Do not pressure test with any control installed. Damage to control can occur due to overpressure.

3.Fill boiler. Vent all air. Pressure test at least 10 minutes at a pressure not less than the following: Steam boiler:

Between 45 and 55 psig. Water boiler:

1½ times maximum allowable working pressure (MAWP) stamped on the boiler nameplate, located on boiler jacket front panel.

Do not exceed above test pressures by more than 10 psig.

Do not leave boiler unattended. Cold water fill could expand and cause excessive pressure, resulting in severe personal injury, death or substantial property damage.

4. Check for maintained gauge pressure and leaks. Repair if found.

Leaks must be repaired at once. Failure to do so can damage boiler, resulting in substantial property damage.

Do not use petroleum-based cleaning or sealing compounds in boiler system. Severe damage to system components can result, causing substantial property damage.

5.Drain boiler and remove air vent, boiler drain and gauge. Remove plugs from tappings that will be used for controls and accessories.

8

Part No. 550-141-935/0602

Image 8
Contents Boiler Manual Contents Before installing boiler Installation must comply withBefore selecting boiler location Lay a foundation, if neededProvide combustion and ventilation air openings For block assembly Using crane attach free end of cables to eye of craneSet boiler in place For packaged boilerInstall back refractory blanket Assemble blockPrepare back section Place a block under pipe to hold section uprightPrepare remaining sections Install intermediate sectionsIf using tankless heater TI sections Perform hydrostatic pressure test Prepare boiler and testInstall cleanout plates Complete block assemblyInstall burner mounting plate on front section Install flue collector Flue collector assemblyInstall collector hold-down bolts Prepare flue collector hood assemblyInstall flue collector Before installing flue collector After installing flue collector, ALL BoilersRear flue boilers only Top flue boilers onlyInstall flue collector General water piping information Install pipingConnect water boiler piping Piping for multiple boilers see Figure Size secondary boiler pump GPM based on following formulasConnect steam boiler piping General steam piping informationConnect steam boiler piping Condensate piping to boiler Condensate receiver capacity Multiple Steam Boiler Piping Gravity Condensate Return Install jacket Before installing jacketInstall support brackets and rails Install jacket front and rear panelsInstall jacket Install jacket trim Install jacket side panelsInstall jacket top panels Jacket side panel placement Models 380, 480, 580 Jacket side panel placement Models 780, 880 Jacket side panel placement Models 1080, 1180, Jacket top panel placement Size piping no smaller than heater inlet and outlet Pipe tankless heatersTo pipe tankless heaters Install water boiler controls Install controlsInstall steam boiler controls Install controls where shown in and FigureWater level control locations see Table Select type of venting system Connect breeching and venting systemsGeneral venting information Construct metal breeching Make final adjustments Install burnerWiring and fuel piping Freeze protection when used Check boiler for gas-tight sealDimensions and ratings Dimensions and ratings Parts Parts Handling ceramic fiber and fiberglass materials Eye Irrigate immediately Breathing Fresh airPropane boilers propane gas odorant All Residential & Commercial Cast Iron Boilers