Weil-McLain 80 manual Set boiler in place, For packaged boiler, For block assembly

Page 5

• Installation • Start-Up • Maintenance • Parts

2 Set boiler in place

For packaged boiler:

1.Remove top jacket panels. Set aside until after boiler is piped.

The boiler contains ceramic fiber and fiberglass materials. Use care when handling these materials per instructions on page 38 of this manual. Failure to comply could result in severe personal injury.

2.Remove lag screws (2 in front, 2 in rear) from shipping rails.

3.Remove boiler from skid. Cables are already attached to block assembly. See Table 2 for lifting weight.

Using crane — hook middle of each cable to eye of crane.

Using hoist — hook middle of each cable to hoist. Raise boiler off skid. Use pipe rollers under skid angles to roll boiler.

4.Place boiler in final position. Center boiler on foundation, if used.

5.Level boiler. Shim under skid angles, if necessary.

6.Cut off cables.

Cables are not intended for long-term usage. Cables may corrode inside boiler, weakening their lifting strength. Failure to remove cables can result in severe personal injury, death or substantial property damage.

7. Proceed to "Perform hydrostatic pressure test," page 8.

Cables are not intended for long-term usage. Cables may corrode inside boiler, weakening their lifting strength. Failure to remove cables can result in severe personal injury, death or substantial property damage.

6.Inspect block assembly for disjointed sections. Check gas-tight seal of flue collector hood and cleanout plates.

Gas tight seal must be maintained to prevent possible flue gas leakage and carbon monoxide emissions, resulting in severe personal injury or death.

a.Check inside section assembly for any light passing through unsealed areas.

b.Mark all unsealed areas.

c.At unsealed areas, check for:

damaged gaskets.

sealing rope not in place.

loose bolts or nuts.

d.Correct all conditions and repeat step b. If unsealed areas still exist, contact your Weil-McLain distributor or sales office before continuing installation.

7.Proceed to "Perform hydrostatic pressure test," page 8.

Table 2 Lifting weights

For block assembly:

1. Remove lag screws (2 in front, 2 in rear) from shipping rails.

2.Remove boiler from skid. Cables are already attached to block assembly. See Table 2 for lifting weight.

• Using crane – attach free end of cables to eye of crane.

Using hoist – attach free end of cables to hoist. Raise boiler off skid. Use pipe rollers under steel skid

angles to roll boiler.

3. Place boiler in final position. Center boiler on foundation, if used.

4.Level boiler. Shim under skid angles, if necessary.

5.Cut off cables.

Part No. 550-141-935/0602

5

Image 5
Contents Boiler Manual Contents Installation must comply with Before installing boilerBefore selecting boiler location Lay a foundation, if neededProvide combustion and ventilation air openings Using crane attach free end of cables to eye of crane For block assemblySet boiler in place For packaged boilerAssemble block Install back refractory blanketPrepare back section Place a block under pipe to hold section uprightPrepare remaining sections Install intermediate sectionsIf using tankless heater TI sections Prepare boiler and test Perform hydrostatic pressure testInstall cleanout plates Complete block assemblyInstall burner mounting plate on front section Flue collector assembly Install flue collectorInstall collector hold-down bolts Prepare flue collector hood assemblyInstall flue collector After installing flue collector, ALL Boilers Before installing flue collectorRear flue boilers only Top flue boilers onlyInstall flue collector General water piping information Install pipingConnect water boiler piping Size secondary boiler pump GPM based on following formulas Piping for multiple boilers see FigureGeneral steam piping information Connect steam boiler pipingConnect steam boiler piping Condensate piping to boiler Condensate receiver capacity Multiple Steam Boiler Piping Gravity Condensate Return Before installing jacket Install jacketInstall support brackets and rails Install jacket front and rear panelsInstall jacket Install jacket trim Install jacket side panelsInstall jacket top panels Jacket side panel placement Models 380, 480, 580 Jacket side panel placement Models 780, 880 Jacket side panel placement Models 1080, 1180, Jacket top panel placement Size piping no smaller than heater inlet and outlet Pipe tankless heatersTo pipe tankless heaters Install controls Install water boiler controlsInstall controls where shown in and Figure Install steam boiler controlsWater level control locations see Table Select type of venting system Connect breeching and venting systemsGeneral venting information Construct metal breeching Make final adjustments Install burnerWiring and fuel piping Check boiler for gas-tight seal Freeze protection when usedDimensions and ratings Dimensions and ratings Parts Parts Eye Irrigate immediately Breathing Fresh air Handling ceramic fiber and fiberglass materialsPropane boilers propane gas odorant All Residential & Commercial Cast Iron Boilers