5 Complete block assembly

Install burner mounting plate on front section

1.Install four ½" x 4¾" studs to secure burner mounting plate to section:

a.Thread and lock together two nuts on rounded end of stud. Thread flat end of stud into one of four holes located around opening.

b.Remove nuts.

c.Repeat steps a and b for remaining studs.

2.Install burner mounting plate:

a.Apply 1/8" continuous bead of sealing rope adhesive in groove around opening in section.

b.Position ½" sealing rope in groove. Overlap ends at least one inch.

c.Install burner mounting plate. Use ½" washers and nuts.

Install observation port assemblies on front and back sections:

1.Install front observation port assembly:

a.Apply 1/8" continuous bead of sealing rope adhesive in groove on observation port.

b.Position 3/8" sealing rope in groove.

c.Secure assembly to section. Use 5/16 " - 18 x ¾" slotted head screws.

2.Repeat above steps for back observation port assembly.

Install cleanout plates

Cleanout plates must be installed gas-tight to prevent possibility of flue gas leakage and carbon monoxide emissions, resulting in severe personal injury or death.

1.See Figure 7. Position two ¼" x 1¾" carriage bolts in cleanout opening. Secure with washers and nuts.

2.Place blanket insulation piece against cleanout plate.

3.Mount cleanout plate over opening. Secure with nuts and washers.

4.Repeat steps 1 through 3 for remaining cleanout plates.

The boiler contains ceramic fiber and

Figure 7 Cleanout plate assembly

fiberglass materials. Use care when

 

handling these materials per

 

instructions on page 38 of this

 

manual. Failure to comply could

 

result in severe personal injury.

 

Part No. 550-141-935/0602

9

Image 9
Contents Boiler Manual Contents Installation must comply with Before installing boilerBefore selecting boiler location Lay a foundation, if neededProvide combustion and ventilation air openings Using crane attach free end of cables to eye of crane For block assemblySet boiler in place For packaged boilerAssemble block Install back refractory blanketPrepare back section Place a block under pipe to hold section uprightInstall intermediate sections If using tankless heater TI sectionsPrepare remaining sections Prepare boiler and test Perform hydrostatic pressure testComplete block assembly Install burner mounting plate on front sectionInstall cleanout plates Flue collector assembly Install flue collectorInstall collector hold-down bolts Prepare flue collector hood assemblyInstall flue collector After installing flue collector, ALL Boilers Before installing flue collectorRear flue boilers only Top flue boilers onlyInstall flue collector Install piping Connect water boiler pipingGeneral water piping information Size secondary boiler pump GPM based on following formulas Piping for multiple boilers see FigureGeneral steam piping information Connect steam boiler pipingConnect steam boiler piping Condensate piping to boiler Condensate receiver capacity Multiple Steam Boiler Piping Gravity Condensate Return Before installing jacket Install jacketInstall support brackets and rails Install jacket front and rear panelsInstall jacket Install jacket side panels Install jacket top panelsInstall jacket trim Jacket side panel placement Models 380, 480, 580 Jacket side panel placement Models 780, 880 Jacket side panel placement Models 1080, 1180, Jacket top panel placement Pipe tankless heaters To pipe tankless heatersSize piping no smaller than heater inlet and outlet Install controls Install water boiler controlsInstall controls where shown in and Figure Install steam boiler controlsWater level control locations see Table Connect breeching and venting systems General venting information Construct metal breechingSelect type of venting system Install burner Wiring and fuel pipingMake final adjustments Check boiler for gas-tight seal Freeze protection when usedDimensions and ratings Dimensions and ratings Parts Parts Eye Irrigate immediately Breathing Fresh air Handling ceramic fiber and fiberglass materialsPropane boilers propane gas odorant All Residential & Commercial Cast Iron Boilers