Heatiator BH60 Draft Test Procedure, Low Draft Adjustment Pot High altitude kit #1-00-232059

Page 25

Installation

Draft

 

Testing Port

Fig. 9

 

“Test”

Low Draft

Adjustment Pot

Fig. 10

High altitude kit #1-00-232059.

Install this ring to increase draft in higher altitude installation locations.

T

Draft Test Procedure

After the venting is completed, the firebox draft will need to be checked and possibly adjusted. After removing the plug bolt from the draft hole (3/16” hex key wrench) shown in Fig. 9, insert the draft meter tube. The hopper lid must be latched during this test. (It is recommended that the draft meter have a scale of 0 to 1” WC.)

Turn the feed adjuster to “Test”. this will start the combustion blower and allow you to check and record the High Draft ______ - IWC date _______ The

maximum draft allowed is -.9” Water Column (-224 Pa). There is no adjustment for the High Draft, other than re-positioning the combustion blower fan blade on its shaft, or a change in the venting configuration.

After the first 60 seconds the “Test” mode lowers the combustion blower voltage to the Low Burn voltage. During this lowered voltage cycle, the Low Draft must be checked and adjusted if necessary. The recommended low draft setting should be between -.45 and -.55 IWC. Depending on the amount of vertical rise, it may not be possible to get a low draft reading in this range. In this case, re-positioning the fan blade further on the motor shaft may be helpful.

There is a low draft voltage adjustment screw located through the small hole to the right of the Igniter Light. See Fig. 10. Adjusted Low Draft is __________ -IWC.

To increase the draft in higher altitudes, kit #

1-00-232059 High Altitude Intake Reduction, may be needed.

Don’t forget to turn the feed adjuster off of “Test”, and reinstall the draft test plug bolt into the boiler.

CAUTION: Hot While In Operation. Do Not Touch. Keep Children, Clothing And Furniture Away. Contact May Cause Skin Burns. See Nameplate And Instructions.

WARNING: Keep Doors Closed During Operation.

WARNING: Do Not Store Fuel or Other Combustible Material Within Installation Clearance Area.

WARNING: Risk of Fire - Do Not Operate With the Flue Draft Exceeding -.9” Water Column (-224 Pa).

25

Image 25
Contents Bio-Flow BH60 Pellet Boiler Installation & Operating ManualPage BH60 Parts Table of Contents Bulk Storage Hopper OptionsPreparation For Installation InstallationBoiler Kit Materials Refer to Minimum non-combustible floor protection area Minimum Clearances To Combustible Materials Requirements for Terminating the Venting VentingVent Pipe VentingVenting Into An Existing Chimney Ventingti gVenting Installation Outside Air Negative Pressure and Electrical Power FailureDomestic HOT Water Zone Installation-PlumbingExtremely Important That this Boiler be Existing Controls and Safety Devices areBoiler AN Existing Operational Boiler Example of Piping in Series withExisting Boiler Associated Piping and Controls That shouldInstallingInstallationDuct/Air-PlumbingConditioning Dipswitch #6 must be on Example of a Typical Forced HOT AIR Heating System Installation With a Hot Air System R1 Relay Splice R2 Relay Installation With a Hot Air System fan only capableOverheat Safety Zone With a 2-wire hot air systemBlue Violet Connection with a wireless thermostatLow Draft Adjustment Pot High altitude kit #1-00-232059 Draft Test ProcedureTest DraftExplanation and Importance of the OverHeat Safety Zone Status light error messagesOperation Control Board Operation Pellet Boiler Outdoor Air Reset Operation Clean Burnpot with scraper Turn Mode Selector to OFFMAX. Temp Flip the Igniter Switch up into the Auto positionType of Fuel Lighting a Fire ManuallyOperation Cleanout cover MaintenanceBurnp ot Fines area Feeder cover FigAsh Removal Inner Refractory LiningOpen The Firebox Door Firebox Baffle Removal CleaningBoiler Must be OFF at the circuit breaker, Combustion Blower CleaningTo Normal Heating Demand Special Insructions/ Power FailureHelpful Hints TroubleshootingFuel BTU Input Range= 0, and 9350 to 60,000 SpecificationsElectrical VAC 60 Hz Plug DiagramPIN ECO-CHOICE Limited Warranty WarrantyEFE Testing LabelBh105 Bh60 Stocked #11 Feeder Assembly Page Quick Reference Auto-Light Signature of Boxer