Figure 20: Wiring Diagram, Steam, McDonnell & Miller PS-801 Probe LWCO for Beckett Burners

BOILER SEQUENCE OF OPERATION WITH PROBE LWCO

When the thermostat calls for heat, it energizes the cad cell primary control, bringing on the burner. The burner will operate in the following sequence: Prepurge for the first 10 seconds; fire until the thermostat is satisfied or the limit setting on the high limit is reached; post-purge for the last 10 seconds. When the high limit control restores the circuit on a drop in pressure, the burner will start if the thermostat is still calling for heat.

The probe low water cut-off will shut down the burner after a 10-15 second delay, if the water level in the boiler drops below the probe level.

The probe low water cut-off will reset and restart the burner with a call for heat a few seconds after the water is re- turned to its normal level.

On burner start, if the cad cell does not see flame within approximately 15 seconds, primary control will shut burner down and enter into a recycle mode, after 60 seconds burner will restart and repeat trial for ignition. If after three

(3)trials for ignition, flame is not detected, control will enter into restricted mode and must be reset manually before burner can be restarted.

When there is no demand for heat, the operating control will maintain the boiler water temperature at the selected set- ting for proper operation of the domestic water heater, if equipped with optional tankless heater.

McDonnell & Miller PS-801

Terminals May Be Lettered or

Numbered as Follows:

Wire

Numbered

Lettered

Color

Terminals

Terminals

 

 

 

RD

5

B

 

 

 

BK

1

H

 

 

 

WH

2

N

 

 

 

Jumper

1-3

H-C

 

 

 

48

Image 48
Contents V8 Series Important Information Read Carefully USA BoilersPage Table of Contents Dimensional Data see Figures 1A Thru 1D V82 thru V89 Water Boiler without Tankless Heater V83 thru V89 Water Boiler with Front Tankless Heater V83 thru V89 Water Boiler with Rear Tankless Heater V83 thru V89 Steam Boiler with or without Tankless Heater Section I PRE-INSTALLATION Page Section II Knockdown Boiler Assembly Removal of Bare Boiler from SkidDo not allow any flueway blockage by gasket Boiler Tapping Locations and Usage Knockdown Boilers Only Knockdown Boiler Jacket Assembly Install Boiler JACKET. See FigureOil Burner Installation Beckett Burner Shown Install Beckett OIL BURNER. See FigureDo not install burner without gasket Install Carlin 102CRD OIL BURNER. See FigureSteam Boilers Only Combustion Head Adjustment Water Boilers OnlyInstall Carlin Elite EZ OIL BURNER. See Figure Installation/Removal of Drawer Assembly Nozzle Replacement Install probe type Low Water Cut-Off Lwco if so equipped Float-Type Low Water Cut-Off Pressure Limit Installation Aquastat bulb must be fully inserted into the wellInstall Trim and Controls with Carlin 102CRD Burner Install Trim and Controls with Carlin Elite EZ Burner Install Trim and Controls with Riello BurnerBurners Supplied by Burnham utilize Page Section III Packaged Boiler Assembly Remove CrateRemove Boiler from Skid Do not drop boiler. Do not bump boiler jacket against floorPage Page Steam or Water Boilers Install Safety or Relief Valve in Tapping M Inspect Nozzle and ElectrodesSection IV Water Boiler Piping and Trim Evaluate the Existing Water SystemPage Recommended Water Piping for Circulator Zoned Heating System Page Page Section V Steam Boiler Piping and Trim Evaluate the Existing Steam SystemPage Section VI Tankless and Indirect Water Heater Piping GPM Alliance Water Heater Piping with V8 Boiler Connect Alliance Indirect Water Heater Piping as shown in BSection VII Venting and AIR Intake Piping General Venting GuidelinesDo not exceed maximum allowable air intake length Recommended Vent Pipe Arrangement and Chimney Requirements Seal all external joints with weatherproof caulk Section Viii Electrical General Boiler Sequence of Operation with Probe Lwco Page Page Jumper Page Page Boiler Sequence of Operation with Float Lwco Page Page Boiler Sequence of Operation Page Page Boiler Sequence of Operation Page Page Boiler Sequence of Operation Page Page Section IX OIL Piping Single Pipe OIL LinesTWO Pipe OIL Lines SINGLE-STAGE Units 3450 RPM TWO Pipe SystemsAlways Inspect Installation Before Starting Burner Section X System START-UPFill Heating System with Water Adjust OIL Burner Before Starting Beckett BurnersCarlin 102CRD Burners Carlin Elite EZ BurnersAdjust OIL Burner While OPERATING. flame present Riello BurnersStart OIL Burner L1 and V1 Head Electrode Check for Clean CUT OFF of Burner Test ControlsCAD Cell Resistance When Sensing Flame Aquastat Switching Action Within L8124C Control Jumper must be removed after this checkAquastat Switching Action Within L8148A Controls Avoid Breathing Fiber Particulates and Dust Section XI Maintenance and Service Instructions Maintenance of LOW Water CUT- OFF DevicesPage Frequent Water Addition Gal/Month V83 V85 V87 V89 V84 V86 V88 14½Page Section XII Boiler Cleaning Clean the Flueways See FigureClean TOP of Boiler Sections if cleaning from the top Clean the Combustion ChamberCleaning of Boiler Flueways Section Xiii Trouble Shooting CombustionOIL Primary Control Section XIV Repair Parts Bare Boiler Assembly Bare Boiler Assembly Bare Boiler Assembly Bare Boiler Assembly 1BBJacket Assembly Page V83 Thru V89 Steam Boilers Trim and Controls V83 Thru V89 Steam Boilers Trim and Controls V82 Thru V89 Water Boilers Trim and Controls V82 Thru V89 Water Boilers Trim and Controls Beckett AFG Burner Beckett OIL Burner Part NOS. for V8 Series Boilers Beckett OIL Burner Part NOS. for V8 Series Boilers Carlin OIL Burner Part Numbers for V8 Series Boilers Burner Specifications XV. LOW Water CUT OFF Lwco WhenService Record Limited Warranty For Residential Cast Iron Steam Boilers