Table 6: Maximum Capacity of Schedule 40 Pipe in CFH for Gas Pressures of 0.5 psig or Less

Length

 

 

0.3 Inch w.c. Pressure Drop

 

 

 

 

0.5 Inch w.c. Pressure Drop

(Feet)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

½

 

 

¾

 

1

 

 

 

½

 

 

 

¾

 

1

 

10

 

 

132

 

 

278

 

520

 

 

1,050

 

175

 

 

360

 

680

 

1,400

20

 

 

92

 

 

190

 

350

 

 

730

 

120

 

 

250

 

465

 

950

30

 

 

73

 

 

152

 

285

 

 

590

 

97

 

 

200

 

375

 

770

40

 

 

63

 

 

130

 

245

 

 

500

 

82

 

 

170

 

320

 

660

50

 

 

56

 

 

115

 

215

 

 

440

 

73

 

 

151

 

285

 

580

60

 

 

50

 

 

105

 

195

 

 

400

 

66

 

 

138

 

260

 

530

70

 

 

46

 

 

96

 

180

 

 

370

 

61

 

 

125

 

240

 

490

80

 

 

43

 

 

90

 

170

 

 

350

 

57

 

 

118

 

220

 

460

90

 

 

40

 

 

84

 

160

 

 

320

 

53

 

 

110

 

205

 

430

100

 

 

38

 

 

79

 

150

 

 

305

 

50

 

 

103

 

195

 

400

Table 7: Equivalent Lengths of Standard Pipe Fittings & Valves

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Pipe

 

 

I.D.

 

 

 

Valves (Fully Open)

 

 

 

 

 

 

Threaded Fittings

 

 

 

 

 

 

 

 

 

 

 

 

Swing

90°

 

45°

 

90° Tee, Flow

90° Tee, Flow

Size

 

(Inches)

Gate

 

Globe

Angle

 

 

 

 

 

 

Check

Elbow

 

Elbow

 

Through Run

Through Branch

 

 

 

 

 

 

 

 

 

 

 

 

 

 

½”

 

0.622

0.35

 

18.6

9.3

 

 

4.3

1.6

 

0.78

 

 

1.0

3.1

¾”

 

0.824

0.44

 

23.1

11.5

 

 

5.3

2.1

 

0.97

 

 

1.4

4.1

1”

 

1.049

0.56

 

29.4

14.7

 

 

6.8

2.6

 

1.23

 

 

1.8

5.3

1¼”

 

1.380

0.74

 

38.6

19.3

 

 

8.9

3.5

 

1.6

 

 

2.3

6.9

Table 8: Specific Gravity Correction Factors

Specific

Correction

Specific

Correction

Gravity

Factor

Gravity

Factor

0.50

1.10

1.30

1.07

0.55

1.04

1.40

1.04

0.60

1.00

1.50

1.00

0.65

0.96

1.60

0.97

0.70

0.93

1.70

0.94

0.75

0.90

---

---

0.80

0.87

---

---

C.Pressure Test. The boiler and its gas connection must be leak tested before placing boiler in operation.

1.Protect boiler gas valve. For all testing over ½ psig, boiler and its individual shut-off valve must be disconnected from gas supply piping. For testing at ½ psig or less, isolate boiler from gas supply piping by closing boiler’s individual manual shut-off valve.

2.Locate leaks using approved combustible gas detector, soap and water, or similar nonflammable solution.

WARNING

Do not use matches, candles, open flames, or other ignition source.

Figure 24: Recommended Gas Piping

30

Image 30
Contents Series 8H 81416021R3-6/10 Price $5.00Important Information Read Carefully Page Table of Contents Dimensional Data Pre-Installation Boiler Model Special Base Part NumberPage II. Boiler Assembly Remove CrateInstallation of Special Base for Combustible Flooring Do not use air to leak test boilerGeneral Assembly Knockdown Boilers Flame Roll-out Switch Installation Install Jacket. See Figure Jacket Assembly EP/OP Control Installation III. Gas Control System Assembly Knockdown Boilers Page Schematic Gas Piping, 24V Standing Pilot, 806H & 807H Main Gas Piping, Intermittent Ignition EI Schematic Pilot Piping Honeywell EI, USA Page Schematic Gas Piping, OP Control System, 806H 810H Schematic Gas Piping, OP-CSD-1 Control System, 808H 810H Page Schematic Gas Piping, EP-CSD-1 Control System, 808H 810H Flow Rate, Temperature Rise, and Pressure Drop IV. Water Trim and PipingDrain Piping Installation Page Page Gas Piping Rated InputConnect boiler gas valve to gas supply system Equivalent Lengths of Standard Pipe Fittings & Valves Specific Gravity Correction FactorsBlocked Vent Switch Installation VI. VentingVent Damper Installation Boiler Equipped With Vent Damper. See FigureIf an Existing Boiler is Removed Typical Vent SystemInstall Boiler Wiring VII. ElectricalHeat Anticipator Settings Sequence of Operation and Wiring Diagrams Page Page Page Page Page Page Wiring Diagram, Honeywell EI, USA, Continuous Circulation Wiring Diagram, Honeywell EI, USA, Intermittent Circulation Wiring Diagram, Honeywell EI, Canada, Continuous Circulation Page Page Page Page Page Page VIII. System Start-Up Lighting Instructions 24V Standing Pilot Operating Instructions EI Lighting Instructions OP Operating Instructions EP Boiler Operating Instructions To Shut Down Honeywell Q314 Pilot Flame 24V Standing Pilot Adjust gas input rate to boiler. Natural Gas Check LimitsInput Rate Install Front Removable Panel Adjust gas input rate to boiler. LP/PropaneClean Heating System Combustion Chamber Burn-OffIX. Service Clean Boiler Flueways. See FigureAvoid Breathing Fiber Particulates and Dust Boiler Flueway Cleaning Pilot Burner LocationHoneywell EI Ignition Module Yellow LED Flame Codes Honeywell EI Ignition Module Green LED Status Codes OFFHoneywell EI Trouble Shooting Guide Repair Parts Heat Exchanger Assembly Canopy Base Assembly Manifold and Main Burners Description Size Quantity Description Quantity Gas Valve, Robertshaw 7000DERHC, Natural Gas, 1 NPT 81660151 Solenoid Gas Valve, Honeywell V8295A1024, ¾ NPT 81660235 Description Quantity Natural Gas Only Pilot Burner, Honeywell Q348A1002, Natural Gas Pilot Burner, Honeywell Q348A1010, LP Gas 8236081 Pipe Tee, 1/8 NPT, Malleable 806601005 Description Size Quantity Brass Compression Coupling, 1/4 OD Tube 8236008 Description Size Quantity Page Jacket Jacket Front Removable Panel Trim and Miscellaneous Controls Draft Hood and Automatic Vent Damper Service Record Service Record Service Record