Ariston 47-116-15 installation instructions Commissioning

Page 15

3.COMMISSIONING

3.1INITIAL PREPARATION

MTS (GB) Limited support the initiative. Within the information pack

you will find a copy of the logbook. It is important that this is completed in the presence of your customer, they are shown how to us it, and it is signed by them. Please instruct your customer that they must have

their logbook with them whenever they contact a service engineer or us.

Preliminary electrical system checks to ensure electrical safety must be carried out by a competent person i.e. polarity, earth continuity, resistance to earth and short circuit.

FILLING THE HEATING SYSTEM:

Remove the panels of the case and lower the control panel (see section 3.3 for further information).

Open the central heating flow and return cocks supplied with the connection kit.

Unscrew the cap on the automatic air release valve one full turn and leave open permanently.

Close all air release valves on the central heating system.

Gradually open valve(s) at the filling point (filling-loop) connection to the central heating system until water is heard to flow, do not open fully.

Open each air release tap starting with the lower point and close it only when clear water, free of air, is visible.

Purge the air from the pump by unscrewing anticlockwise the pump plug and also manually rotate the pump shaft in the direction indicated by the pump label to ensure the pump is free.

Close the pump plug.

Continue filling the system until at least 1 bar registers on the pressure gauge.

Inspect the system for water soundness and remedy any leaks discovered.

FILLING OF THE D.H.W. SYSTEM:

Close all hot water draw-off taps.

Open the cold water inlet cock supplied with the connection kit.

Open slowly each draw-off tap and close it only when clear water, free of bubbles, is visible

GAS SUPPLY:

Inspect the entire installation including the gas meter, test for soundness and purge, all as described in BS 6891:1988.

Open the gas cock (supplied with the connection kit) to the appliance and check the gas connector on the appliance for leaks.

When the installation and filling are completed turn on the central heating system (section 3.4) and run it until the temperature has reached the boiler operating temperature. The system must then be immediately flushed through.

The flushing procedure must be in line with BS 7593:1992 code of practice for treatment of water in domestic hot water central heating systems.

During this operation, we highly recommend the use of a central heating flushing detergent (Fernox Superfloc or equivalent), whose function is to dissolve any foreign matter that may be in the system.

Substances different from these could create serious problems to the pump or other components.

The use of an inhibitor in the system such as Fernox MB-1 or equivalent is strongly recommended to prevent corrosion (sludge) damaging the boiler and system.

Failure to carry out this procedure may invalidate the appliance warranty.

15

Image 15
Contents Installation Instructions Type C Boilers Table of Contents General Information Overall View Installation Overall Dimensions Supply must be fused at 3 a Domestic Water Morley Road TonbridgeKent TN9 1RA 80 mm Extension Piping not insulated Piping insulated Restrictor Extension Piping not insulated Piping insulatedSystems Restrictor No RestrictorCalculating the lengths of the pipes, Electrical Diagram Central Heating Return Commissioning Control Panel Initial START-UP Operational Adjustments Status ANTI-FROST Device 16.0 GAS AdjustmentsMethane Liquid Gas Butane G20 Gas G30Maintenance Boiler MiscellaneousProgrammer Technical Service Hot Line 01494 Technical InformationManufacturer Merloni TermoSanitari SpA Italy Servicing Instructions Type C Boilers Fault Finding Removing the front panel Servicing InstructionsRemoving the side panels Removing the sealed chamber frontal coverRemoving the combustion cover Removing the burner and jetsRemoving the electrodes Removing the main heat exchanger Removing the fan Removing the air pressure switchSetting pressure for soft ignition Setting the gas pressuresSetting the minimum and the maximum power of the boiler Setting the maximum heating circuit powerRegulating the heating power for Natural gas G20 Regulating the heating power for Butane gas G30Regulating the heating power for Propane gas G31 Removing the spark generator Removing the D.H.W. secondary exchanger Removing the gas valveRemoving the safety valve Removing the main circuit flow switchRemoving the automatic air vent Removing the pump Removing the expansion vessel Removing the pressure gaugeRemoving the overheat thermostat Removing the D.H.W. temperature sensor N.T.CRemoving the heating temperature sensor N.T.C Removing the D.H.W. flow switchRemoving the time clock Checking the fusesRemoving the P.C.B Finding diagrams described in this chapter Fault FindingYES YES ∆ P 1.2 mbar YES Electrical Diagrams MicroGENUS 23/27 Mffi MicroGENUS 23/27 Mffi Ariston Page Manufacturer Merloni TermoSanitari SpA Italy Microgenus 27 Mffi Cod Part Code Description 998924 Panel combustion chamber front 571770 Main flow switch top cap