(NOTE: Some termination caps may cause the vent pipe to be off center on flashing). Ensure that proper clearances to combustible materials are maintained. If you are not using an approved termination cap with a built-in standoff on a building with vinyl siding, a vinyl siding standoff should be installed between the termination cap and the exterior wall (Figure 5.8). Follow manufacturer’s instructions for attaching the vinyl siding standoff to the horizontal termination cap. The vinyl siding standoff prevents excessive heat from possibly melting the vinyl siding material. The vent terminal cap shall not be recessed into a wall or siding. Remove siding from the area where the standoff will be located.

Note: The attachment from the vent pipe to the vent termination cap must be sealed with silicone. Termination caps shall not be recessed into a wall or siding.

WARNING

Fire Hazard.

Exhaust Fume Risk.

Impaired Performance of Appliance.

Ensure vent components are locked together correctly.

Pipe may separate if not properly joined.

VINYL SIDING

Apply sealant to all four sides

SCREWS

Bolt horizontal top to vinyl standoff

SCREWS

WALL THIMBLE COVER

Vinyl siding standoff with siding beneath removed

WALL THIMBLE

Figure 5.8

WARNING

Do NOT connect a pipe section to a termination cap without using the telescoping flue section found on the termination cap.

WARNING

Burn Risk.

Local codes may require installation of a cap shield to prevent anything or anyone from touching the hot cap.

Step 5.

Place the wall thimble cover over the pipe assembly and slide the appliance and vent assembly towards the wall, carefully inserting the vent pipe into the vent termination cap assembly. It is important that the vent pipe extend into the vent termination cap a sufficient distance so as to result in a minimum pipe overlap of 1-1/4 in. (32mm). Secure the connection between the vent pipe and the vent termination cap by attaching the two sheet metal strips extending from the vent termination cap assembly into the outer wall of the vent pipe. Use the two sheet metal screws provided to connect the strips to the pipe section (Figure 5.9).

1/4 in. (6mm)

Fold Strap Here

Sheet Metal Screw

Wall Thimble Cover/Ceiling

Firestop as Required by Local

JurisdictionStrap

Wall Thimble

Figure 5.9

Page 14

Heat & Glo · Tiara Petite B · 7026-101K

August 1, 2008

Image 14
Contents Hot glass will cause burns Installation and OperationWhat to do if you smell gas Congratulations Location Hang tag attached to rear of applianceTable of Contents 1Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Tools and Supplies Needed Design & Installation ConsiderationsGetting Started Inspect Appliance & ComponentsClearances to Combustibles Appliance Location and ClearancesSelecting Appliance Location 4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Use of Elbows Vent InformationVenting Components Measuring StandardsHow to Use the Vent Graph Venting GuidelinesHorizontal Termination Step203mm Vinyl Siding Vertical Termination Direct Vent PipeCeiling Joists Framing 2 in mm Long Wood Screws Twist-lock the vent cap and seal Cathedral Ceiling Level Cathedral Ceiling Support BoxClass a Metal Chimney Existing Masonry Chimney Type C Up & Out InstallationType a & B Co-Axial to Co-Linear Type D Hearth MountCut and bend flashing as needed to fit Sealant adhesive Flex Liner Flex Coupler Sheet Metal Screws Assembling Slim Line Trim Ring and Heat Shield Installing Slim Line Trim Ring and Heat ShieldSlim Line Wall Thimble NextFIG. C Minimum Clearance Fuel Conversions Wire clipGas Information Converting to LP GasValve Regulator Replacement Screws Rubber Gasket Identification Label FGas Pressures Gas ConnectionHigh Altitude Installations Standing Pilot Ignition System Wiring Recommendation for WireConnecting to the Appliance Wire Size Max. LengthIgnition Module Access and Battery Replacement To access the moduleLeg Leveling System Appliance SetupRemove Shipping Materials Flue Restrictor Installation Intake Air Shutter Adjustment Intake Damper Operation Positioning the LogsAccessories Mineral WoolBlower Installation KIT ContentsAugust 1 Heat & Glo · Tiara Petite B · 7026-101K 19 Complete Assembly Warming Shelves Installation Glass ReplacementControls Operating InstructionsBefore Lighting Appliance For Your Safety Read Before Lighting Lighting ApplianceAfter Appliance is Lit Frequently Asked QuestionsInitial Break-in Procedure Troubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Appliance After servicingMaintenance Tasks Inspect Necessary. USE Caution When CLEANING/HANDLING Ceramic BurnerAppliance Dimension Diagram Reference MaterialsVent Components Diagram SL-D Series Vent ComponentsVent Components List HHT SL-PTermination Caps & Kits Tiara Petite B DescriptionService Parts List cont’d. Tiara Petite B Tiara Petite B Cast Parts Individual Pieces Accessories Service and Maintenance Log Date of Service Performed By Description of ServiceWarranty Policy Limited Lifetime Warranty Heat & GLO GAS Appliance ProductsDealer Telephone Tiara Petite BContact Information