I. Install RF4-8

The RF4-8 may be used in place of the roof flashing and storm collar (Sections 10.G. and 10.H.)

Pipe must be supported within 12 in. (305 mm) of the roofline using plumbers strapping or an SLP-FS when us- ing the RF4-8 Flashing. Refer to Sect. 8.C. Securing Vent Sections.

Secure with 4 screws no longer than 1/2 in./13 mm

SLP-FS

Figure 10.18 Secure Pipe with SLP-FS

Trim the rubber boot (using scissors or a utility knife), cutting along the marked measurement lines. See Figure 10.19. Use the 150 mm line for SLP, 210 mm for DVP.

Lubricate pipe or flue with water and slide the flashing down. It may be necessary to trim the top shingles around the base of the rubber boot to ensure a good fit.

Draw around flashing, remove.

Apply silicone sealant to roof inside the lines (Figure 10.20)

Lubricate pipe or flue with water and slide flashing down. Seat firmly in sealant. Nail roof flashing to the roof.

Apply silicone sealant on the top outside of the base plate on the sides and on top edge. See Figure 10.21. Install shingles, Apply sealant at the top edge of the rubber boot. See Figure 10.22.

We recommend that you top coat with conventional acrylic house paint to improve the appearance of your galvanized base flashing.

Figure 10.19 Trim Rubber Boot

Figure 10.20 Apply Sealant

Apply Sealant

Top & Partial Sides

Figure 10.21 Slide Flashing Down, Secure & Apply Sealant

Silicone Sealant

(top of boot)

 

 

 

Shingles Trimmed

Flashing over

Shingles over

Shingles

 

 

Flashing

 

 

Figure 10.22

Installation Complete

46

Heatilator • Caliber Mesh CD Series-SIT Valve • 4040-849 Rev J • 06/08

Image 46
Contents Direct Vent Gas Appliance Installation and OperationModels CD4236MR CD4842MR What to do if you smell gasCongratulations Homeowner Reference InformationInstaller Guide Table of ContentsUser Guide Troubleshooting Appliance SetupReference Materials Gas Appliance Fireplace Limited Lifetime Warranty Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Operating Instructions Gas Fireplace SafetyYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceFor Your Safety Read Before Lighting Lighting Instructions IPIStanding LightingPilot Frequently Asked Questions After Fireplace is LitRemote Control Maintenance and ServiceMaintenance Tasks-Homeowner Doors, Surrounds, FrontsMaintenance Tasks-Qualified Service Technician Getting Started Typical Appliance SystemTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Select Appliance Location Framing and ClearancesModel # Construct the Appliance Chase ClearancesMantels Mantel and Wall ProjectionsMantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesMinimum Clearances for Termination Vent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsTop Vent Horizontal Termination Vent DiagramsOne Elbow Two 45 Elbows replacing One 90 Elbow Two ElbowsInstalled Vertically Three ElbowsTop Vent Vertical Termination No Elbow12 ft 3.66 m min 60 ft 18.29 m max Rear Vent Horizontal Termination One 45 ElbowTwo Elbows Rear Vent Vertical Termination Min Ft 1.83 m max 12 ft 3.66 m min 60 ft 18.29 m max Install Vertical Termination Baffle 17 Flat BaffleWall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Installing Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Convert from Top Vent to Rear VentOuter Collar, Remove Four Screws 11 Place Outer Collar on Rear of Appliance 16 Cover Plate-Replace Secure and Level the Appliance 20 Proper Positioning, Leveling And Securing Of AnAssemble Pipe Sections DVP Only Install Vent PipeAttach Pipe to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Only Assemble Slip Sections Secure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 SLP-FSInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap InteriorGas Pressure Gas InformationFuel Conversion Gas ConnectionIntellifire Ignition System Wiring Wiring RequirementsStanding Pilot Ignition System Wiring Optional Accessories RequirementsElectrical Service and Repair WSK-MLT-HTLJunction Box Installation Wall Switch Installation for Fan OptionalFacing Material FinishingCombustible Appliance Setup Removing Fixed Glass Assembly Install the Log AssemblyReplacing Fixed Glass Assembly Install Hood Install TrimInstall Clean Face Components Install Top Latch CoverInstall Bottom Latch Cover Air Shutter SettingInstall Firescreen Assembly Troubleshooting Standing Pilot Ignition SystemSymptom Possible Cause Corrective Action Intellifire Ignition System Will not ignite. If the pilot Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP Vent ComponentsBEK DVP-BEK2 DVP-TVHW DVP-TRAP DVP-HRC-SS Effective SL-2DVP Adapter#22 Log/Grate Assembly ServiceParts CD4842M Series Parts Service CD4842M SeriesOptional Components Model # Description Contact Information