D. Install Attic Insulation Shield

WARNING! Fire Risk. DO NOT allow loose materials or insulation to touch vent. Hearth & Home Technologies Inc. requires the use of an attic shield.

The National Fuel Gas Code ANSI Z223.1 and NFPA 54 requires an attic shield constructed of 26 gauge minimum metal that extends at least 2 in. (51 mm) above insulation.

Attic shields must meet specified clearance and be se- cured in place.

Flat Ceiling Installation

• Remove one shield from box.

NOTICE: Cut previously installed batt insulation to make room for the attic insulation shield.

Wrap shield around pipe if pipe is already installed in area to be insulated.

Match the three holes in each side and fasten with three screws to form a tube.

Bend three tabs on the bottom of the shield outward to allow attachment to the ceiling firestop.

Bend the remaining bottom tabs inward 90º to maintain the air space between the pipe and the shield. Set the shield on the ceiling firestop and attach to the firestop.

Bend all tabs inward 90º around the top of the shield. These tabs must be used to prevent blown insulation from getting between the shield and vent pipe, and to maintain air space clearance.

Vaulted Ceiling Installation

• Remove one shield from box.

NOTICE: Cut previously installed batt insulation to make room for the attic insulation shield.

Cut the attic insulation shield (if application is for vaulted ceiling) to fit your ceiling pitch. Snip cut edge to recreate 1 in. bend tabs all the way around the bottom.

Wrap shield around pipe if pipe is already installed in area to be insulated.

Match the three holes in each side and fasten with three screws to form a tube.

Bend three tabs on the bottom of the shield outward to allow attachment to the ceiling firestop.

Bend the remaining bottom tabs inward 90º to maintain the air space between the pipe and the shield. Set the shield on the ceiling firestop and attach to the firestop.

Bend all tabs inward 90º around the top of the shield. These tabs must be used to prevent blown insulation from getting between the shield and vent pipe, and to maintain air space clearance.

BEND ALL TABS INWARD 90°

TO MAINTAIN CLEARANCE

AND PREVENT INSULATION

FROM FALLING INSIDE

 

BEND 3 TABS

 

OUTWARD TO

 

FASTEN TO CEILING

 

FIRESTOP-BEND

 

REMAINING TABS

 

INWARD 90 DEGREES

 

TO MAINTAIN

INSERT 3

CLEARANCE

 

SCREWS

 

Figure 8.5 Attic Insulation Shield

38

Hearth & Home Technologies • DV3732SBI, DV3732SBIL • 2215-900 Rev. F • 9/12

Image 38
Contents HOT Surfaces ModelsWhat to do if you smell gas Congratulations Homeowner Reference InformationTable of Contents User GuideFinishing Appliance SetupTroubleshooting Reference MaterialsLimited Lifetime Warranty Hearth & Home Technologies Inc Limited Lifetime WarrantyLimited Lifetime Warranty Warranty ConditionsListing and Code Approvals Requirements for the Commonwealth of Massachusetts Your Fireplace Gas Fireplace SafetyOperating Instructions User Guide Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Decorative Doors and FrontsWhat to do if YOU Smell GAS Lighting Instructions IPIFinal inspection by GAS ValveAfter Fireplace is Lit Frequently Asked QuestionsIssue Solutions Maintenance and Service Logs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection FireboxGetting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMinimum FT. Maximum Mantel and Wall ProjectionsMinimum Minimum UnlimitedTermination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Minimum Clearances for TerminationVent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsUse of Flex Vent Vent Diagrams Top Vent Horizontal Termination One Elbow Fire RiskInstalled Horizontally Top Vent Horizontal Termination Two ElbowsTop Vent Horizontal Termination Three Elbows V1 Minimum H1 Maximum H1 + H2 MaximumTop Vent Vertical Termination No Elbows V1 = 60 ft. Max .3 m Exhaust restrictor InstructionsTop Vent Vertical Termination Two Elbows Three Elbows Minimum MaximumTop Vent Vertical Termination Four 90º Elbows V1 MIN H1 MAX V2 MIN H2 MAX V3 MINPage Rear Vent Horizontal Termination Two Elbows MAX MIN + H 2 MAXRear Vent Vertical Termination One Elbow Rear Vent Vertical Termination Three elbows MIN MAX + H 2 MAXClearances to Combustibles Prior to installing the gas applianceCoaxial to Colinear Venting Termination Cap Flue DamperRear Vent Connecting the DV-46DVA-GCL Adapter to Appliance Top VentConnecting the LINK-DV30B to the DV-46DVA-GCL adapter Wall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Top VentRear Vent Cut the metal retaining band and fold the sides outSecuring and Leveling the Appliance 13 Proper Positioning, Leveling And SecuringAssemble Vent Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components SLP only Install Horizontal Termination Cap DVP and SLP Pipe DVP-HPC1 DVP-HPC2Gas Pressure Gas InformationFuel Conversion Gas ConnectionElectrical Information Wiring RequirementsOptional Accessories Requirements Code CSA C22.1Intellifire Ignition Wiring Diagram with Remote Junction Box Installation Wall Switch Installation for Fan OptionalSplatter Guard To install the Splatter GuardFinishing To Close the Lower Access Panel To Remove the Splatter GuardTOP View 16 Noncombustible Facing Diagram Facing MaterialDoors TemplateElevated Hearth Systems Appliance Setup Install the Log Assembly Slot aMate slot C with tab C Mate slot with locating screw Air Shutter Setting Install Louvers and TrimInstall Hood Air Shutter SettingsIntellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Ues to spark, and main Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP-AS2DVP-TRAP DVP vent componentsDVP-TRAPFL RF6M RF12MBEK DVP-BEK2 COOL-ADDDVP-TV DVP-TB1 DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAPSLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP  B. Vent Components Diagrams SL-2DVP SLK-SNKD DVP-FBHT SLP-CCS-BK SLP-DCF-BKSLP-FLEX-TRAP SLP-TVHW SLP-LPC Optional Wire HarnessPVI-SLP LINK-DV30B DVP-2SL DV-46DVA-GCLGas Fireplace DV Service Parts ListAt Depot #12 Valve Assembly Service PartsContact Information