B. Assemble Vent Sections (SLP Pipe Only)

To attach the first vent component to the starting collars of the appliance:

Lock the vent components into place by sliding the pipe section onto the collar.

Align the seam of the pipe and seam of collar to allow engagement. Rotate the vent component to lock into place. Use this procedure for all vent components. See Figure 10.5.

Slide the gasket over the first vent section and place it flush to the appliance. This will prevent cold air infiltration. Caulk with a minimum of 300ºF continuous exposure rating may be used to hold the part in place.

Continue adding vent components, locking each succeeding component into place.

Ensure that each succeeding vent component is securely fitted and locked into the preceding component.

Commercial, Multi-family (Multi-level exceeding two sto- ries), or High-Rise Applications

For Installation into a commercial, multi-family (multi-level exceeding two stories) or high-rise applications: All outer pipe joints must be sealed with silicone with a minimum of 300ºF continuous exposure rating, including the slip section that connects directly to the horizontal termination cap.

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections. See Figure 10.1

Only outer pipes need to be sealed. All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed in this manner, unless otherwise stated.

WARNING! Risk of Fire or Explosion! DO NOT break silicone seals on slip sections. Use care when remov- ing termination cap from slip pipe. If slip section seals are broken during removal of the termination cap, vent may leak.

Note: Align seams to engage pipe, then rotate counterclockwise to lock

Figure 10.5 Adding Venting Components

C. Assemble Slip Sections

Slide the inner flue of the slip section into the inner flue of the pipe section and the outer flue of the slip section over the outer flue of the pipe section. See Figure 10.6.

Slide together to the desired length.

Pilot hole

Figure 10.6 Slip Section Pilot Holes

Maintain a 1-1/2 in. (38 mm) overlap between the slip section and the pipe section.

Secure the pipe and slip section with two screws no longer than 1/2 in. (13 mm), using the pilot holes in the slip section. See Figure 10.7.

Figure 10.7 Screws into Slip Section

Continue adding pipe as necessary following instructions in “Assembling Pipe Sections.”

NOTICE: If slip section is too long, the inner and outer flues of the slip section can be cut to the desired length.

NOTICE: When installing a vent system with an HRC termination cap, all pipe system joints shall be sealed using a silicone sealant with a minimum of 300ºF continuous exposure rating.

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections.

Only outer pipes are sealed, sealing the inner flue is not required.

All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed.

Hearth & Home Technologies • DV3732SBI, DV3732SBIL • 2215-900 Rev. F • 9/12

43

Image 43
Contents What to do if you smell gas ModelsHOT Surfaces Homeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty Limited Lifetime Warranty Hearth & Home Technologies IncWarranty Conditions Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Operating Instructions User Guide Gas Fireplace SafetyYour Fireplace Decorative Doors and Fronts Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance and Service Firebox Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection LogsTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseMinimum Unlimited Mantel and Wall ProjectionsMinimum Minimum FT. MaximumVent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Covered Alcove ApplicationsUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyUse of Flex Vent Fire Risk Vent Diagrams Top Vent Horizontal Termination One ElbowTop Vent Horizontal Termination Two Elbows Installed HorizontallyV1 Minimum H1 Maximum H1 + H2 Maximum Top Vent Horizontal Termination Three ElbowsExhaust restrictor Instructions Top Vent Vertical Termination No Elbows V1 = 60 ft. Max .3 mMinimum Maximum Top Vent Vertical Termination Two Elbows Three ElbowsV1 MIN H1 MAX V2 MIN H2 MAX V3 MIN Top Vent Vertical Termination Four 90º ElbowsPage MAX MIN + H 2 MAX Rear Vent Horizontal Termination Two ElbowsRear Vent Vertical Termination One Elbow MIN MAX + H 2 MAX Rear Vent Vertical Termination Three elbowsTermination Cap Flue Damper Prior to installing the gas applianceCoaxial to Colinear Venting Clearances to CombustiblesConnecting the LINK-DV30B to the DV-46DVA-GCL adapter Connecting the DV-46DVA-GCL Adapter to Appliance Top VentRear Vent Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP SLP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Top Vent Appliance PreparationCut the metal retaining band and fold the sides out Rear Vent13 Proper Positioning, Leveling And Securing Securing and Leveling the ApplianceAssemble Pipe Sections Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Vent Sections DVP Pipe OnlyAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingInstall Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination DVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeGas Connection Gas InformationFuel Conversion Gas PressureCode CSA C22.1 Wiring RequirementsOptional Accessories Requirements Electrical InformationIntellifire Ignition Wiring Diagram with Remote Wall Switch Installation for Fan Optional Junction Box InstallationFinishing To install the Splatter GuardSplatter Guard To Remove the Splatter Guard To Close the Lower Access PanelTOP View Facing Material 16 Noncombustible Facing DiagramTemplate DoorsElevated Hearth Systems Appliance Setup Slot a Install the Log AssemblyMate slot C with tab C Mate slot with locating screw Air Shutter Settings Install Louvers and TrimInstall Hood Air Shutter SettingSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Ues to spark, and main Reference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP vent components DVP-TRAPCOOL-ADD RF6M RF12MBEK DVP-BEK2 DVP-TRAPFLDVP-TV SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAPDVP-TB1  B. Vent Components Diagrams SL-2DVP SLP-FLEX-TRAP SLP-TVHW SLP-CCS-BK SLP-DCF-BKSLK-SNKD DVP-FBHT LINK-DV30B DVP-2SL DV-46DVA-GCL Optional Wire HarnessPVI-SLP SLP-LPCAt Depot Service Parts ListGas Fireplace DV Service Parts #12 Valve AssemblyContact Information