Baxi Potterton BBU 15 HE Condensate Disposal, Condensate Pump Operation, From Boiler 500mm Min

Page 19

Termination via internal discharge branch e.g sink waste - downstream

Direct Connect Fitting

Pipe must terminate

 

above water level but

 

below surrounding surface

Sink

 

From Boiler

Fig. 13

Termination to an internal soil and vent pipe

Direct Connect Fitting

5.0Site Requirements

5.10Condensate Disposal (cont.)

9.Ensure that the condensate can discharge freely (without blockage or restriction of the pipe) into the drain.

10.Examples are shown of condensate pipe methods of termination:-

i)via an internal discharge branch (e.g. sink waste) - Fig. 13.

ii)to an internal or external soil and vent pipe - Fig. 14.

iii)to a drain or gully - Fig. 15. Ensure that the condensate can discharge freely (without blockage or restriction of the pipe) into the drain.

iv)to a soakaway - Fig. 16.

From Boiler

Min. 450mm

Fig. 14

Termination to a drain or gully

Pipe must terminate above water level but below surrounding surface

From Boiler

Fig. 15

500mm Min.

Termination to a purpose made soak-away

From Boiler

Fig. 16

Holes in the soak-away must face away from the building

5.11Condensate Pump Operation

1.The pump operates for 2 seconds when mains voltage is applied to the boiler, e.g. when the power has been interrupted and then reinstated.

2.If the boiler reset rocker switch has been operated the pump will run also for 2 seconds.

3.When the level of condensate in the sump is sufficient to activate the discharge float switch the pump will run for 7 seconds, during which time about 0.6 litres of condensate will be discharged.

4.In the event of condensate not being discharged the safety float switch will operate when the volume of condensate in the sump reaches 1.05 litres. Once the safety float switch has been activated the boiler will lockout.

5.The total volume of the sump is 1.5 litres.

© Baxi Heating UK Ltd 2009

19

Image 19 Contents
Baxi Bermuda BBU 15 HE 0086 Scheme Members only Installer Notification GuidelinesLegislation Important Installation, Commissioning, Service & RepairCodes of Practice, most recent version should be used Safe Manual Handling Contents Introduction ContentsDescription Layout Fig General LayoutFlue Kit 10m & 12.5m a Bermuda HE Cbbu 15 HE Technical DataThere is a drain cock supplied in the plumbing kit System DetailsWater Circulating Systems Treatment of Water Circulating SystemsSystem Controls PipeworkStorage Systems Sealed Systems Figs , 7 Sealed Systems Fireplace Opening & Surround Site RequirementsBuilders Opening Fig LocationNo Horizontal Runs are Permitted FlueElectrical Connection Gas Connection VentilationGas Supply Fig Electrical Supply FigCondensate Disposal Fig Condensate Drain GeneralFrom Boiler 500mm Min Total volume of the sump is 1.5 litresCondensate Disposal Condensate Pump OperationBoiler Internal Illustrated Wiring Diagram Boiler Internal WiringInitial Preparation InstallationFlue System Barb ‘C’ Clip Air Cowl Air Duct Collar Ribs Terminal Cap Electrical Connection Siting the BoilerWater Connections Gas ConnectionCompletion Completion & CommissioningCommissioning the Boiler Test Point Annual Servicing Annual ServicingAnnual Servicing Inspection Spark Generator Fig Electrode Assembly FigChanging Components Changing ComponentsBurner Spark Generator Plug Gas Feed Pipe Injector Fan FigBurner Fig Spark Generator Plug Electrode Fan InjectorGas Valve Fig Injector Gas Valve Earth WireNTC Fig Safety Thermostat FigFloat Switches Fig PCB FigSetting the Gas Valve CO2 check Setting the Gas ValveFlue Sampling Point Display Control Knobs Initial Fault Finding Checks Fault FindingError Codes Go to section ‘A’ Error 110 flashingBurner lights Press the Service Reset Switch for 5 secondsSpark gap and position Check wiring Clean condensate drain systemX2 connector, is 230V AC across Terminals 1 Voltage at PCB X2 connector isReplace flame sensing electrode Replace Safety ThermostatShort Parts List 13.0 Short Parts ListPage Page Page GAS Boiler System Commissioning Checklist Date Energy Efficiency Checklist completed? Service RecordAfter Sales Service 0844 871 Warranty & ServiceSerial Number Date of Installation Installer Details name, address and contact numbers