American Water Heater HCG3 130T 300 Inch Concentric Termination Sidewall Installation

Page 29

6 Inch Concentric Termination Installation

6” x 4” STANDARD

INTAKE AIR CONNECTION

REDUCER

BUSHING

6” or 4” PVC

INTAKE AIR PIPE

 

 

 

6” x 6” x 6”

 

VENT TERMINAL

 

 

 

Y FITTING

 

 

 

 

 

WITH SCREEN

 

 

 

 

 

 

 

VENT PIPE

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

11.Push the vent cap/vent pipe assembly into the intake air Y fitting assembly until the vent cap seats properly on the large diameter intake air pipe. Ensure the vent pipe is cemented to the no stop-lip reducer bushing previously installed in the Y fitting. Secure the vent cap to intake air pipe with field supplied stainless steel screws. Install the screws through the pre-drilled holes in the vent cap brackets. Pilot holes for the screws must be drilled in the intake air pipe to prevent damage/cracking.

 

 

VENT

6” x 4” NO STOP-LIP

VENT CAP

 

CONNECTION

REDUCER BUSHING

STAINLESS STEEL

4” PVC

 

 

VENT PIPE IS 4 INCH SCHEDULE 40 PVC

SUPPLIED LENGTH 46 1/2 INCHES (118 cm)

MAXIMUM ALLOWABLE LENGTH 66 1/2 INCHES (169 cm)

MINIMUM ALLOWABLE LENGTH 33 1/8 INCHES (84 cm)

INTAKE AIR PIPE IS 6 INCH SCHEDULE 40 PVC

SUPPLIED LENGTH 25 3/8 INCHES (64 cm)

MAXIMUM ALLOWABLE LENGTH 45 3/8 INCHES (115 cm)

MINIMUM ALLOWABLE LENGTH 12 INCHES (30 cm)

INTAKE AIR PIPE

Y FITTING ASSEMBLY

VENT CAP

VENT PIPE ASSEMBLY

6 INCH CONCENTRIC TERMINATION KIT

SEVEN PIECE KIT - FIELD ASSEMBLY REQUIRED

COMBUSTION

AIR

ROOF FLASHING (field supplied)

INTAKE

AIR PIPE

VENT

MAINTAIN 12” (30 cm)

 

 

 

 

18” (45 cm) FOR CANADA

 

 

 

 

MINIMUM CLEARANCE

 

 

 

 

ABOVE HIGHEST ANTICIPATED

 

 

 

 

 

 

 

 

SNOW LEVEL. MAXIMUM OF

 

 

 

 

24” (60 cm) ABOVE ROOF.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

STRAP (field supplied)

NOTE: SECURING STRAP

MUST BE FIELD INSTALLED

TO PREVENT MOVEMENT

OF TERMINATION KIT

VENT

PIPE

Figure 29

Assemble and install the 6 inch concentric termination. Refer to Figure 29, Figure 30 and Figure 31 for these instructions:

1. Cement the Y fitting to the larger diameter intake air pipe.

6 INCH CONCENTRIC TERMINATION

VERTICAL INSTALLATION

Figure 30

2.

Cement the 6” x 4” no stop-lip reducer bushing into the

 

straight (vent) end of the Y fitting.

3.

If the intake air piping being installed is 4 inch pipe, cement

 

the 6” x 4” standard reducer bushing into the angle (intake

 

air) end of the Y fitting as shown in Figure 29.

4.

If the intake air piping being installed is 6 inch pipe discard

 

the 6” x 4” standard reducer bushing. The 6 inch intake air

 

piping will connect directly to the angle end of the Y fitting.

5.

Slide the intake air Y fitting assembly from inside the building

 

through the hole cut for the termination in the roof or sidewall.

 

Ensure no foreign materials such as insulation accumulate

 

inside the assembly.

6.

Secure the intake air Y fitting assembly using field supplied

 

metal strapping or equivalent support materials.

7.

On installations installed through the roof slide a field

NOTE: SECURING STRAP MUST BE FIELD INSTALLED TO PREVENT MOVEMENT OF TERMINATION KIT IN SIDEWALL.

STRAP

VENT(field supplied)

PIPE

INTAKE

AIR PIPE

COMBUSTION

AIR

VENT

1 INCH

MAXIMUM

 

supplied plumbing boot or roof flashing over the intake air Y

 

fitting assembly and secure it to the roof.

8.

Seal around the plumbing boot or roof flashing.

9.

Slide the steel vent cap onto the 4 inch vent pipe and cement

 

the vent terminal to the end of the vent pipe.

10.

Slide the vent cap back up the vent pipe until it touches the

 

vent terminal. Secure the vent cap to the vent pipe using field

 

supplied stainless steel screws. Pilot holes must be drilled for the

 

screws to prevent damage/cracking of the vent pipe. Apply water

 

proof silicone sealant between the vent cap and the terminal.

6 INCH CONCENTRIC TERMINATION

SIDEWALL INSTALLATION

Figure 31

12.Connect the intake air and vent piping from the water heater to the 6 inch concentric termination. Use field supplied 4 inch couplings or 6” x 4” reducer couplings as needed.

13.Return to Direct Vent Installation on page 23 to complete the installation of the intake air and vent piping between the concentric termination and the water heater.

29

Image 29
Contents Commercial gas water heaters Table Of Contents Optional Safe Installation, Use and ServiceANSI/NSF-5 Hydrogen Gas Flammable General Safety InformationPrecautions Fire and Explosion Hazard Fire or Explosion HazardQualified Installer or Service Agency Preparing For The InstallationIntroduction Abbreviations UsedBasic Operation Features And ComponentsTop View Components Top ViewSide Views Rough In Dimensions Installation ConsiderationsRecovery Capacities Gas Line Connection SizeLocating The Water Heater Service ClearanceClearance To Combustible Materials Intake Air and Vent Pipe ClearancesOptional Concentric Terminations Extended Vent TerminationsHard Water Circulation PumpsPower Supply Installation RequirementsGas Pressure Requirements Supply Gas LineDishwashing Machines Mixing ValvesClosed Water Systems Thermal ExpansionValve Discharge Pipe Requirements Temperature-Pressure Relief ValveCombustible Material Storage Condensate DrainContaminated Air Condensate Drain Water TrapConfined Space Air RequirementsUnconfined Space Outdoor Air Through Two Openings Fresh Air Openings For Confined SpacesOutdoor Air Through One Opening Outdoor Air Through Two Horizontal DuctsPage Inspection Commonwealth of MassachusettsGeneral Venting Instructions Venting InstallationGeneral Venting Information Venting Requirements Direct Vent Installation Venting Installation SequencePower Vent Installation Intake AIR Screen Balance Plate Vertical Termination InstallationVertical Termination Direct Vent Sidewall Termination Installation Sidewall Termination InstallationInch Concentric Termination Flat Roof Clearance Concentric Termination InstallationInch Concentric Termination KIT Inch Concentric Termination InstallationVent Pipe is 4 Inch Schedule 40 PVC Inch Concentric Termination Sidewall InstallationThree Concentric Terminations TWO Concentric TerminationsFour Concentric Terminations Eight Concentric TerminationsEight Concentric Terminations Multiple Concentric Termination ArrangementsTwo Concentric Terminations Direct Vent Horizontal Power Vent HorizontalVenting Arrangements Direct Vent Horizontal Concentric Direct Vent Vertical Vent Horizontal IntakeDirect Vent Horizontal Vent Vertical Intake Power Vent Termination Clearances Sidewall Power VentDirect Vent Termination Clearances Sidewall Direct VentCondensate Drain Installation Water Heater InstallationInstallation Notes Installation InstructionsGas Line Sizing Supply Gas Line InstallationSupply Gas Line Sizing U. S. Units Supply Gas Line Sizing Metric UnitsGas Line Connection Supply Gas Regulator InstallationGas Line Leak Testing Power Supply Connections Electrical WiringEnable/Disable Circuit Connecting An External Supervisory ControlWater Line Connections Water Piping DiagramsValve Discharge Pipe Thermometers not SuppliedHigh Temperature Limit Control ECO Temperature RegulationHigh Temperature Applications Thermostat ControlOverview Control System OperationControl System Navigation User Input ButtonsIcon Description Status IconsState Description Operating StatesControl System Menus Menu DescriptionUpdate Cancel User Settings & Control System MenusBack Help Description/Action DisplayChange Back Help Heater Information Description/Action Display Display Settings Description/ActionView Back Help Back AdvancedECO YESService Contact Information UpdateSelect Back Help NameInitial Start Up Start UpPrior to Start up Manifold Gas Pressure Adjustment Supply Gas Pressure AdjustmentMultiple Appliance Installations To Turn Off Gas High Altitude InstallationsChecking The Firing Rate Honeywell Lighting The Water HeaterLighting & Operation Label Sequence Of Operation TroubleshootingInstallation Checklist YES no Sequence Of Operation Flow ChartInstallation Errors Operational ProblemsRough Starting, Rough Operation Momentary IgnitionFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesBlower Prover Failure Maintenance Schedule MaintenanceGeneral Draining And FlushingLime Scale Removal Filling The Water HeaterSediment Removal Drain Valve and Access Panels Powered Anode RodsTemperature-Pressure Relief Valve Test Vent SystemCCB Central Control Board Layout DiagramsUser Interface Modul AHCG3 130T 300 Wiring DiagramUser AHCG3 130T 400 Wiring DiagramCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water American Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty