American Water Heater HCG3 130T 300 TWO Concentric Terminations, Three Concentric Terminations

Page 30

Multiple Concentric Termination Clearances

When installing multiple concentric terminations vertically through a roof or horizontally through a sidewall ensure the required clearances (separation) between terminations are maintained. Ensure multiple terminations are arranged or grouped as required.

Note: These clearances must be maintained to prevent the recirculation of vent (exhaust) gases to the intake air. Clearances are measured between the edges of the concentric termination caps.

When installing multiple concentric terminations through a roof or through a sidewall the clearances shown in Figure 32 must be maintained.

See Multiple Concentric Termination Arrangements on page 31.

Close Proximity & Standard Clearance

1.The clearance between multiple termination caps must be 0 inches (touching) to a maximum of 2 inches (5 cm), dimension A - Figure 32, when installing concentric terminations in close proximity. See Figure 37 on page 31.

2.The clearance between multiple termination caps must be increased to a minimum of 24 inches (61 cm), dimension B - Figure 32, when installation in close proximity (above) is not possible. This is the standard clearance.

 

 

 

CONCENTRIC

 

 

 

A

TERMINATION CAPS

 

B

END VIEW

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

OR

CLOSE PROXIMITY

STANDARD CLEARANCE

A = 0 - 2 INCHES (0 - 5 cm)

B = 24 INCHES (61 cm)

 

OR GREATER

TWO CONCENTRIC TERMINATIONS

(THROUGH A ROOF OR SIDEWALL)

Figure 32

Three Concentric Terminations

1.When installing three concentric terminations through a roof or through a sidewall the third termination may be installed in close proximity as indicated by dimension A in Figure 33.

2.If close proximity installation of the third termination is not possible the third termination may be installed as indicated by dimension B in Figure 33.

TERMINATIONCONCENTRIC

A

B

CAPS END VIEW

 

 

A

 

THIRD

 

 

TERMINATION

A = 0 - 2 INCHES (0 - 5 cm)

B = 24 INCHES (61 cm)

CLOSE PROXIMITY

OR GREATER

THREE CONCENTRIC TERMINATIONS

(THROUGH A ROOF OR SIDEWALL)

Figure 33

Four Concentric Terminations

1.When installing four concentric terminations through a roof or through a sidewall in close proximity they may be arranged into stacked rows of two as shown in Figure 34 or lateral rows of two as shown in Figure 35.

2.Four is the maximum number of concentric terminations that may be installed in a group where all terminations are in close proximity as shown in Figure 34.

A

A

CONCENTRIC

TERMINATION

CAPS END VIEW

A = 0 - 2 INCHES (0 - 5 cm)

CLOSE PROXIMITY

FOUR CONCENTRIC TERMINATIONS

(THROUGH A ROOF OR SIDEWALL)

Figure 34

A B A

CONCENTRIC

TERMINATION

CAPS END VIEW

A = 0 - 2 INCHES (0 - 5 cm)

B = 24 INCHES (61 cm)

CLOSE PROXIMITY

OR GREATER

FOUR CONCENTRIC TERMINATIONS

(THROUGH A ROOF OR SIDEWALL)

Figure 35

Groups Of Terminations

1.When installing multiple groups of concentric terminations through a roof or through a sidewall in close proximity they can be installed into stacked groups of four as shown in Figure 36. Lateral groups of four as shown in Figure 35 may be a more convenient installation arrangement for multiple groups depending on available space.

CONCENTRIC

A B TERMINATION

CAPS END VIEW

A

A = 0 - 2 INCHES (0 - 5 cm)

B = 24 INCHES (61 cm)

CLOSE PROXIMITY

OR GREATER BETWEEN

 

GROUPS OF FOUR

EIGHT CONCENTRIC TERMINATIONS

(THROUGH A ROOF OR SIDEWALL)

Figure 36

30

Image 30
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ANSI/NSF-5Optional General Safety Information PrecautionsHydrogen Gas Flammable Fire or Explosion Hazard Fire and Explosion HazardIntroduction Preparing For The InstallationQualified Installer or Service Agency Abbreviations UsedFeatures And Components Basic OperationTop View Top View ComponentsSide Views Recovery Capacities Installation ConsiderationsRough In Dimensions Gas Line Connection SizeClearance To Combustible Materials Service ClearanceLocating The Water Heater Intake Air and Vent Pipe ClearancesHard Water Extended Vent TerminationsOptional Concentric Terminations Circulation PumpsGas Pressure Requirements Installation RequirementsPower Supply Supply Gas LineClosed Water Systems Mixing ValvesDishwashing Machines Thermal ExpansionTemperature-Pressure Relief Valve Valve Discharge Pipe RequirementsContaminated Air Condensate DrainCombustible Material Storage Condensate Drain Water TrapAir Requirements Unconfined SpaceConfined Space Outdoor Air Through One Opening Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through Two Horizontal DuctsPage Commonwealth of Massachusetts InspectionVenting Installation General Venting InformationGeneral Venting Instructions Venting Requirements Venting Installation Sequence Power Vent InstallationDirect Vent Installation Vertical Termination Installation Intake AIR Screen Balance PlateVertical Termination Direct Vent Sidewall Termination Installation Sidewall Termination InstallationConcentric Termination Installation Inch Concentric Termination Flat Roof ClearanceInch Concentric Termination Installation Inch Concentric Termination KITInch Concentric Termination Sidewall Installation Vent Pipe is 4 Inch Schedule 40 PVCFour Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Eight Concentric TerminationsMultiple Concentric Termination Arrangements Two Concentric TerminationsEight Concentric Terminations Power Vent Horizontal Venting ArrangementsDirect Vent Horizontal Direct Vent Vertical Vent Horizontal Intake Direct Vent Horizontal Vent Vertical IntakeDirect Vent Horizontal Concentric Termination Clearances Sidewall Power Vent Power VentTermination Clearances Sidewall Direct Vent Direct VentInstallation Notes Water Heater InstallationCondensate Drain Installation Installation InstructionsSupply Gas Line Sizing U. S. Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing Metric UnitsSupply Gas Regulator Installation Gas Line Leak TestingGas Line Connection Enable/Disable Circuit Electrical WiringPower Supply Connections Connecting An External Supervisory ControlValve Discharge Pipe Water Piping DiagramsWater Line Connections Thermometers not SuppliedHigh Temperature Applications Temperature RegulationHigh Temperature Limit Control ECO Thermostat ControlControl System Navigation Control System OperationOverview User Input ButtonsStatus Icons Icon DescriptionControl System Menus Operating StatesState Description Menu DescriptionBack Help User Settings & Control System MenusUpdate Cancel Description/Action DisplayChange Back Help Display Settings Description/Action Heater Information Description/Action DisplayECO Back AdvancedView Back Help YESSelect Back Help UpdateService Contact Information NameStart Up Prior to Start upInitial Start Up Supply Gas Pressure Adjustment Multiple Appliance InstallationsManifold Gas Pressure Adjustment High Altitude Installations Checking The Firing RateTo Turn Off Gas Lighting The Water Heater Lighting & Operation LabelHoneywell Troubleshooting Installation ChecklistSequence Of Operation Sequence Of Operation Flow Chart YES noRough Starting, Rough Operation Operational ProblemsInstallation Errors Momentary IgnitionFault And Alert Conditions Fault And Alert Messages Possible Causes Check/Repair Displayed Fault/Alert MessageBlower Prover Failure General MaintenanceMaintenance Schedule Draining And FlushingFilling The Water Heater Sediment RemovalLime Scale Removal Temperature-Pressure Relief Valve Test Powered Anode RodsDrain Valve and Access Panels Vent SystemDiagrams CCB Central Control Board LayoutAHCG3 130T 300 Wiring Diagram User Interface ModulAHCG3 130T 400 Wiring Diagram UserCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water American Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty