American Water Heater HCG3 130T 300 User Settings & Control System Menus, Back Help

Page 45

User Settings & Control System Menus

Temperatures Menu

Operating Set Point And Differential Adjustment

The Operating Set Point is adjustable from 90°F (42°C) to 180°F (82°C). The factory setting is 120°F (49°C). The Differential is adjustable from 2° to 20°. The factory setting is 8°. These user settings are accessed from the Temperatures menu. The following instructions will explain how to adjust these settings and navigate the control system menus.

When the water temperature sensed by the control system from the two (upper and lower) Temperature Probes reaches the Operating Set Point the control system will end the heating cycle. A heating cycle will be activated again when the sensed water temperature drops below the Operating Set Point minus the Differential setting.

Note: Lower Differential settings may cause excessive heating cycles (short-cycling) which can cause premature failure of components such as the Hot Surface Igniter. Set the Differential at the highest setting which produces an acceptable hot water supply. Set the Operating Set Point to the lowest setting which produces an acceptable hot water supply for most efficient use.

Description/Action

Display

 

 

From the Desktop screen, press the Operational Button under

 

 

 

MANUFACTURER / MODEL INFORMATION

 

MENU. The "Main Menu" screen will be displayed.

 

 

 

 

 

Tank Temperature

120°F

 

Operating Set Point

120°F

 

Status: Standby

 

 

 

 

 

MENU

 

HELP

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Main Menu is where all control system menus are listed,

 

 

 

 

 

 

 

 

 

 

 

 

Main Menu

 

 

 

 

see Table 13 on page 44 for a complete list and description of

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

control system menus. Use the Up and Down Buttons to view

 

Temperatures

 

 

 

 

 

 

 

 

 

 

all control system menus from the Main Menu.

 

 

 

 

 

 

 

 

 

 

Heater Status

 

 

 

 

 

 

 

 

 

 

 

 

With Temperatures menu selected (highlighted in black) in

 

Display Settings

 

 

 

 

the Main Menu screen, press the Operational Button under

 

Heater Information

 

 

 

 

“SELECT” to enter the Temperatures menu.

 

 

 

 

 

If the Temperatures menu is not selected use the Up and Down

 

Current Fault

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Buttons to select this menu item.

 

 

 

 

 

 

 

 

 

 

 

SELECT

 

BACK

HELP

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

With the Operating Set Point selected in the Temperatures

Temperatures

 

menu, press the Operational Button underneath “CHANGE” to

 

Operating Set Point

 

120°F

activate the adjustment mode for this menu item.

 

If Operating Set Point is not selected use the Up and Down

Differential

 

8°F

Tank Temperature

 

120°F

Buttons to select this menu item.

Upper Temperature

 

122°F

 

 

Note: Higher Temperature settings increase wear and

Lower Temperature

 

118°F

(Heater Regulated to Tank)

 

operating costs. Set the Operating Set Point to the lowest

 

Upper Probe Offset

 

0°F

setting which produces an acceptable hot water supply. This

 

will always provide the most energy efficient operation and

CHANGE

BACK

HELP

longer life.

 

 

 

With the adjustment mode for the Operating Set Point activated

Temperatures

 

the selection bar will change from a black fill to a black outline.

 

Operating Set Point

 

140°F

Use the Up and Down Buttons to change the current setting.

 

Differential

 

8°F

Press the Operational Button under "UPDATE" to save the

Tank Temperature

 

120°F

Upper Temperature

 

122°F

new setting. Press the Operational Button under "CANCEL" to

 

Lower Temperature

 

118°F

discard changes and return to the previously saved setting.

 

(Heater Regulated to Tank)

 

 

 

Note: Use this same procedure to change the Differential

Upper Probe Offset

 

0°F

setting and other adjustable user settings in the control system

UPDATE

 

CANCEL

menus.

 

 

 

 

45

Image 45
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ANSI/NSF-5Optional General Safety Information PrecautionsHydrogen Gas Flammable Fire and Explosion Hazard Fire or Explosion HazardQualified Installer or Service Agency Preparing For The InstallationIntroduction Abbreviations UsedBasic Operation Features And ComponentsTop View Components Top ViewSide Views Rough In Dimensions Installation ConsiderationsRecovery Capacities Gas Line Connection SizeLocating The Water Heater Service ClearanceClearance To Combustible Materials Intake Air and Vent Pipe ClearancesOptional Concentric Terminations Extended Vent TerminationsHard Water Circulation PumpsPower Supply Installation RequirementsGas Pressure Requirements Supply Gas LineDishwashing Machines Mixing ValvesClosed Water Systems Thermal ExpansionValve Discharge Pipe Requirements Temperature-Pressure Relief ValveCombustible Material Storage Condensate DrainContaminated Air Condensate Drain Water TrapAir Requirements Unconfined SpaceConfined Space Outdoor Air Through Two Openings Fresh Air Openings For Confined SpacesOutdoor Air Through One Opening Outdoor Air Through Two Horizontal DuctsPage Inspection Commonwealth of MassachusettsVenting Installation General Venting InformationGeneral Venting Instructions Venting Requirements Venting Installation Sequence Power Vent InstallationDirect Vent Installation Intake AIR Screen Balance Plate Vertical Termination InstallationVertical Termination Direct Vent Sidewall Termination Installation Sidewall Termination InstallationInch Concentric Termination Flat Roof Clearance Concentric Termination InstallationInch Concentric Termination KIT Inch Concentric Termination InstallationVent Pipe is 4 Inch Schedule 40 PVC Inch Concentric Termination Sidewall InstallationThree Concentric Terminations TWO Concentric TerminationsFour Concentric Terminations Eight Concentric TerminationsMultiple Concentric Termination Arrangements Two Concentric TerminationsEight Concentric Terminations Power Vent Horizontal Venting ArrangementsDirect Vent Horizontal Direct Vent Vertical Vent Horizontal Intake Direct Vent Horizontal Vent Vertical IntakeDirect Vent Horizontal Concentric Power Vent Termination Clearances Sidewall Power VentDirect Vent Termination Clearances Sidewall Direct VentCondensate Drain Installation Water Heater InstallationInstallation Notes Installation InstructionsGas Line Sizing Supply Gas Line InstallationSupply Gas Line Sizing U. S. Units Supply Gas Line Sizing Metric UnitsSupply Gas Regulator Installation Gas Line Leak TestingGas Line Connection Power Supply Connections Electrical WiringEnable/Disable Circuit Connecting An External Supervisory ControlWater Line Connections Water Piping DiagramsValve Discharge Pipe Thermometers not SuppliedHigh Temperature Limit Control ECO Temperature RegulationHigh Temperature Applications Thermostat Control Overview Control System Operation Control System Navigation User Input ButtonsIcon Description Status IconsState Description Operating StatesControl System Menus Menu DescriptionUpdate Cancel User Settings & Control System MenusBack Help Description/Action DisplayChange Back Help Heater Information Description/Action Display Display Settings Description/ActionView Back Help Back AdvancedECO YESService Contact Information UpdateSelect Back Help NameStart Up Prior to Start upInitial Start Up Supply Gas Pressure Adjustment Multiple Appliance InstallationsManifold Gas Pressure Adjustment High Altitude Installations Checking The Firing RateTo Turn Off Gas Lighting The Water Heater Lighting & Operation LabelHoneywell Troubleshooting Installation ChecklistSequence Of Operation YES no Sequence Of Operation Flow ChartInstallation Errors Operational ProblemsRough Starting, Rough Operation Momentary IgnitionFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesBlower Prover Failure Maintenance Schedule MaintenanceGeneral Draining And FlushingFilling The Water Heater Sediment RemovalLime Scale Removal Drain Valve and Access Panels Powered Anode RodsTemperature-Pressure Relief Valve Test Vent SystemCCB Central Control Board Layout DiagramsUser Interface Modul AHCG3 130T 300 Wiring DiagramUser AHCG3 130T 400 Wiring DiagramCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water American Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty