Contents
Installation
Installation Instructions
Pre-Installation Checklist
Do not Lift the Door By the Handle
Cutout for 27″ 68.6 cm Single Built-In Ovens only
For JKS10, JKP30, JKP70, PK916, ZEK938 models only
Cutout for 27″ 68.6 cm Double Built-In Ovens only
For JKP35, JKP55, JKP75, PK956, ZEK958 models only
Must Support 150 LBS Kg
Cabinetry
Cutout for 27″ 68.6 cm Single Ovens only
Side by Side Installations
Cutout for 30″ 76.2 cm Single Built-In Ovens only
Cutout for 30″ 76.2 cm Double Built-In Ovens only
Approved to be installed under
Cabinetry
Cutout for 30″76.2 cm Single Ovens only
Electrical Connections
B3 New Construction Four-Conductor Branch Circuit Connection
B4 Three-Conductor Branch Circuit Connection
C2 Drilling the Pilot Holes and Mounting the Oven
Securing the Oven in the Opening
C1 Sliding the Oven Into the Opening
C3 Preparing for the Bottom Trim Installation
C4 Installing the Metal Bottom Trim
Replacing the Oven Door
Operation Checklist
Pre-Test Checklist
Page
De instalación
¿Preguntas? Visite nuestro sitio en la Web ge.com
Instrucciones de instalación
Lista de control antes de la instalación
Corte para los hornos de una unidad de 27″ 68,6 cm solamente
49 11/16 126,2 cm Mín 50 1/8 127,3 cm Máx
Debe Soportar 150 Libras
Gabinetes
Horno individual de 27″ 68,6 cm
Corte para los hornos de una unidad de 30″ 76,2 cm solamente
Instalaciones de lado a lado
Desde el piso 12 30,5 cm
Debe Soportar 150 Libras 68 Kg
Gabinetes
Horno individual de 30″ 76,2 cm
Conexiones eléctricas
Atención AL Instalador
B4 Conexión de circuito ramal de tres conductores
C2 Cómo taladrar los orificios piloto y montar el horno
Posición firme del horno en la abertura
C1 Cómo deslizar el horno en el interior de la abertura
C3 Preparación para la instalación de la moldura de fondo
Cómo instalar la puerta del horno
Lista de control antes de la prueba
Lista de control para la operación
Notas