Figure 1-1 Pilot Assembly, Flame Adjustment

a.This test requires a DC millivolt meter set to a scale of 0-1000mv. Using test leads with sharp probes will help in taking the required reading.

b.Locate the thermopile wires coming from the thermostat/limit box going to the gas valve. The wire insulation size decreases near the gas valve connections.

c.Using the positive (+) test probe, connect the probe to High Limit wire terminal. On UFM systems pierce High Limit wire insulation at the gas valve safety magnet connection.

d.Connect the negative (-) test probe to pilot tubing.

e.Remove the pilot flame adjustment cover.

f.Turning the flame adjusting screw clockwise lowers the flame and the millivolt output. Turning the screw counterclockwise increases flame size and millivolt output.

g.Rotate the screw in the direction to achieve a reading of 400 ±50 mv.

NOTICE

Allow 3 to 5 minutes between flame adjustments to allow the reading to settle.

h.Replace the pilot flame adjusting screw cover.

1.5.2.2Electronic Ignition Pilot Systems - There is nothing to manually light on the electronic ignition systems. Pilot ignition is controlled by the electronic pilot system.

a.Open the gas supply valves to the fryer.

b.Turn the thermostat control knob counterclockwise to the OFF position.

1-10

Image 19
Contents TheresAlwaysSomethingCooking Page For Your Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Safety Table of Contents Section Title Operating Instructions Owner Maintenance and AdjustmentsList of Tables and Figures Page Which Fryer do I HAVE? General Information and InstallationLeg Installation and Adjustment Assembly and LevelingChecking Your NEW Fryer Drainboard Installation Heat Deflector InstallationSplashback Installation Flue InstallationInstallation Clearances InstallationGas Connection Page Electrical Connection Ventilation and Fire Safety SystemsANSI/UL Visual Checks Initial AdjustmentsBurner Ignition Systems OFF Page Page Insufficient GAS Pressure Normal Flow Main Burner SystemInsufficient Flow Excessive FlowPage Initial Cleaning Thermostat Calibration Check Standard Thermostat Calibration Solid State Thermostat CalibrationPage Page Filling the Fryer With Solid Shortening Operating InstructionsFilling the Fryer Filling the Fryer With Liquid ShorteningFryer Shut-Down Operating InstructionsFryer Start-Up Do not Start Fryer Without Filling with OILDaily Cleaning Power FailurePage Weekly Fryer Cleaning Boil OUT Owner Maintenance and AdjustmentsPage Fryer does not work Fryer Troubleshooting