2 BEFORE STARTING THE INSTALLATION
This section provides general installation considerations, unpacking and inspection procedures, and lists the tools and materials required for cabinet installation.
2.1Installation Overview
Installation of the
Installing a Support
•Fiberglass Mounting Sleeve
•Poured Concrete
Mounting the
Feeder and Distribution Cable
Connector Panel
Splitter
2.2Unpacking and Inspection
This section provides instructions for opening the shipping boxes, verifying that all parts have been received, and verifying that no shipping damage has occurred.
Use the following procedure to unpack and inspect the cabinet and all accessories:
1.Open the shipping carton(s) and carefully unpack the cabinet and any accessories from the protective packing material.
2.Open the cabinet doors (requires 216B key tool) and check for broken or missing parts. If there are damages, contact ADC (see Section 13) for an RMA (Return Material Authorization) and to reorder if replacement is required.