ADCP-96-015 • Issue 1 • July 2004

6.Open the rear door of the cabinet and remove the back section of the cabinet bottom cover as described in Section 5.1. Then return to step 7 of this procedure to finish mounting the cabinet.

7.Using appropriate lifting equipment, hold the cabinet in position over the pad (see Figure 11) so the cabinet is suspended over the rectangular opening in the top of the ground spacer or PMF.

8.Feed each distribution cable into the appropriate conduit section and route to the splice enclosure (not provided).

Note: The cables are coiled on spools for shipment. On each spool is a label that lists each fiber subunit within the cable and the connector panels where each subunit is terminated. After the cable is unspooled, label each cable with the corresponding fiber subunit and connector panel designations. In addition, tag or label the stub end of each cable so that the cable can be identified after being routed to the splice enclosure.

Note: A separate splice enclosure (not provided) is required for splicing the cabinet OSP distribution cables to the system OSP distribution cables.

9.Lower the cabinet onto the ground spacer or PMF and align the mounting holes in the cabinet base with the threaded holes in the spacer or PMF.

10.If the installation includes a ground spacer, secure the cabinet to the spacer using the four hex bolts, four flat washers and four nuts provided with the spacer. If the installation does not include a ground spacer, secure the cabinet to the PMF using the four hex bolts, lock flat washers, and four flat washers provided with the cabinet. Tighten all fasteners securely.