ADCP-96-015 • Issue 1 • July 2004

Note: Make sure all remnants of concrete are removed from the PMF prior to mounting the cabinet. It is not necessary to use shims to level or align the cabinet as long as the top surface of the PMF is clean and free of any installation debris.

2.If a ground spacer will not be installed, proceed to step 7. If a ground spacer (accessory) will be installed, align the ends of the left ground spacer section with the ends of the right ground spacer section and then press the two sections together.

3.Place the assembled ground spacer in position for mounting on the PMF as shown in Figure 11.

ACE-142S

CABINET (FRONT)

HEX BOLTS, FLAT

WASHERS, AND

NUTS (4 PLACES)

 

GROUND

CAPSCREWS, LOCK

SPACER

(ACCESSORY)

WASHERS, AND FLAT

 

WASHERS (4 PLACES)

 

CONCRETE

 

PAD

 

 

19816-A

PAD MOUNTING

FRAME (PMF)

CABLE

CONDUIT

Figure 11. Mounting the ACE-142V Cabinet on the Concrete Pad

4.Align the mounting holes in the ground spacer with the mounting holes in the PMF.

5.Secure the ground spacer to the PMF using the four capscrews, four lock washers, and four flat washers provided with the cabinet. Tighten all capscrews securely.

Page 20

© 2004, ADC Telecommunications, Inc.