ADCP-96-015 • Issue 1 • July 2004

2.3Cabinet Installation Hardware

The cabinet is shipped with fasteners (see Table 4) for securing the ACE-142S/142V cabinet to the FMS or the PMF.

Table 4. Cabinet Installation Fasteners

ITEM

QUANTITY

 

 

3/8 x 1-inch hex head capscrews

4

 

 

3/8-inch flat washers

4

 

 

3/8-inch lock washers

4

 

 

2.4Tools and Materials Required for Installation

The following tools and materials are required for cabinet installation:

All Installations

9/16-inch wrench

Hammer

Wire cutter

Utility knife

Screwdriver (flat blade)

Tape measure

Pen or marker

216B key tool (required to open cabinet door)

Padlock (optional)

Grounding system, copper wire, and grounding clamp (per local requirements)

Splicing equipment for splicing OSP feeder and distribution cables

Lifting equipment for hoisting the cabinet into position for mounting

Fiberglass Mounting Sleeve Installations

Fiberglass Mounting Sleeve (FMS), FMS sleeve cover, FMS adapter cover (see Table 2)

Excavation and earth moving equipment

Stone aggregate

Tamping equipment

Level

Hole saw and drill (use to cut holes for cable conduit if pre-drilled holes are not usable)

Landscaping equipment and site restoration supplies

Page 6

© 2004, ADC Telecommunications, Inc.