Electrical Requirements

Ferrite Ring InstallationGas and Steam OPL Micro Control Models Only

The ferrite ring provided in the literature packet must be installed over the power leads during connection of electrical service. The ferrite protects the sensitive electronic controls from destructive electrical disturbances which may be present on power lines to the machine. Failure to properly install the ferrite ring may result in damage to the electronic controls and will void control warranty.

To Install:

1.Immediately after connection of power leads and before applying power to machine, locate each of the incoming service leads including ground.

2.Snap the ferrite ring closed over all of the service leads inside of the control tray as shown. It is important that the ferrite ring be installed inside the control tray. Refer to Figure 14. Do not install the ferrite outside of the box or other area. Make sure that service leads are in the center of the ferrite before closing the ring so as not to pinch or damage leads.

2

1

}

3

T383I

1Ferrite Ring

2Electrical Connections V.A.C.~

3Ground Wire

Figure 14

70269701

© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT

51