Electrical Installation – Communication Wiring to EPO and Optional Equipment

Pin connections J108 (for EPO wiring options)

EPO switch wiring. The UPS must be connected to either a dry contact or a 24VDC Emergency Power Off (EPO) switch.

Connect the EPO cable, using one of the following 4 wiring configurations.

1:Dry Contracts Normally Open

J108

1

2

3

4

5

6

EPO circuit

EPO is activated when pin 1 is connected to pins 3, and 5

2: +24V Normally Open

3:Dry Contacts Normally Closed

J108

1EPO circuit

2

3

4

5

6

J108

1

2

3EPO circuit

4

5

6

EPO is activated when an isolated SELV 24VDC voltage is supplied on pin 1 with reference to pin 2.

EPO is activated when a connection from pin 3 to pin 5 is opened

4:+24V Normally Closed

J108

1

2

3

4

5

6

EPO circuit

EPO is activated when a SELV 24VDC voltage removed from pin 3 with reference to pin 5

36

Smart-UPS® VT 10-30 kVA, 208/220 V Site Preparation and Installation Manual 990-1598B

Page 42
Image 42
American Power Conversion 208/220 installation manual Pin connections J108 for EPO wiring options, +24V Normally Closed