Wiring Verification Procedure
Do not connect batteries in the UPS.
Note
Use following procedure to verify that the UPS has been wired properly:
1. If your installation includes an XR Enclosure, make sure that the DC breaker (if
available) is in the OFF position and that both 125A fuses are removed from the XR Enclosure.
2. Check that the power wiring is torqued to 45 lbf.in/7Nm.
3. If your installation includes an XR Enclosure, remount the 125A fuses in the XR Enclosure and check that the DC breaker (if available) on the XR Battery
Enclosure is in the ON position.
4. Please leave a wiring diagram on site for service / technical support personnel.