Run the Cables

Connect Power in Installations with Busbars

Warning: Before carrying out the steps below, you must follow the Total Power Off procedure in the Operation manual.

Install isolators

See “Specifications” on page 23 for torque specification.

The isolators separate the baying kit busbar from the six vertical busbars in each XR Battery Enclosure, and the (+), N, and (-) busbars in the UPS. This is how the isolators are fitted to their busbar:

1.Guide the isolator busbar through the adjacent side panels.

+

N

2.Position the isolators across the vertical busbars (N in this example) and then fasten the isolator busbar by using the provided M5 Torx screws.

3.Secure the isolator to its busbar with cable ties.

+

N

 

N

 

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation