9Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation
Note: The U-shaped interconnection brackets are 1-2 mm higher than the opening below the
enclosure to inactivate the casters. Therefore, the enclosure must be tilted when placing the U-
shaped interconnection brackets under the enclosure.
3. In each side of the same enclosure insert a
maximum of nine and a minimum of two M8
screws (not provided) through holes in the
bottom of the enclosure and through holes in the
U-shaped floor anchoring brackets, and into the
pre-drilled floor holes.
Note: See “Prepare for Floor-Anchoring
(optional)” on page2 if the floor has not been prepared for anchoring.
4. Fasten the screws.
5. Move the adjacent enclosure on its
casters close to the enclosure with the U-
shaped floor anchoring brackets.
Note: If the additional enclosure is on
its levelling feet, use a forklift or pallet jack to move it into position.