Pre-installation: at the site
Before beginning the installation, verify that you have all the equipment on site by comparing the list of items ordered against the items in the boxes. Your project manager can supply you with an inventory list. Do not rely solely on the packing slips inside the boxes.
The
●Verify that the open,
●Verify that the rail kit to support the media server is available for installation.
●Verify that the rail kit, required to support the very heavy UPS, is installed on the rack or available for installation. For information on installing the rails, see the documentation that comes with the rail kit.
●Verify that the equipment rack(s) is(are) grounded per local code. See Job Aid: Approved Grounds
●Verify that the customer provides AC power to the rack from a nonswitched outlet.
●Verify that cabling between the TN8400AP and the TN8412AP (SIPI) circuit packs is in place.
Equipment specifications
The S8400 Media Server control network components consist of a G650 Media Gateway with a TN8400AP circuit pack installed in slot 2, a TN8412AP (SIPI) installed in slot1, and one UPS. See Table 1: Control network components specifications.
Table 1: Control network components specifications
Component | Dimensions | Metric (cm) | U (height) | Weight (lb/kg) |
| English (in.) |
|
|
|
|
|
|
|
|
Media Gateway: | 14h x 17.5w x 22d | 30h x 56w x 48d | 8 | 39/18 |
G650 | ||||
|
|
|
|
|
UPS: | 3.5h x 17w x 19d | 9h x 43w x 48d | 2 | 34/15 |
700 VA | ||||
1500 VA | 3.5h x 17w x 24d | 9h x 43w x 61d | 2 | 50/23 |
|
|
|
|
|
Installing and Configuring the Avaya S8400 Media Server | February 2006 13 |