PROGRAMMING FUNCTIONS - LEVEL 2 (cont.)
34.When finished, press the other batch size and repeat step # 33.
35.When finished setting both batch sizes, press and release DONE.
36.The display should now read LAST ON:. Adjust the LAST ON TIME using
37.When finished, press the other batch size and repeat step # 36.
38.When finished setting both batch sizes, press and release DONE.
39.The display will show the three times just entered. Press and release each batch size to display the set- tings for that batch. If the 1ST ON TIME is set to OFF, the display will read PULSE BREW DISABLED. After a 5 second delay, the display will read 2 BATCHES
DONE?
40.If both the pulse brew settings for both batch sizes are not correct, press and release NO to return to the 1ST ON TIME setup screen and repeat steps 24 through 39.
41.If both batch sizes are correct, press YES. The display should now read DRIP TIME.
Setting DRIP TIME:
NOTE: Drip time also controls the solenoid on time for models with optional funnel locks.
42.The display should now read DRIP TIME, along with either the word OFF or a time showing. A batch light will also be blinking.
43.Using
44.When finished, press the other batch size and repeat step #43.
45.When finished setting both batch sizes, press and release DONE. The display should read 2 BATCHES
DONE?
46.Select YES. The screen should show the name of the recipe being programmed (modified) along with SETUP COMPLETE (except for ITCB w/Sweet meter, step # 47).
Setting SWEET METER: Optional on ITCB
This function allows the operator to adjust the amount of sweetener added to the dilution water. The solenoid is pulsed on/off for the duration of the dilution cycle. Setting #1 will produce the least amount of sweetener (weakest) and (#14) being the most (strongest).
Procedure:
47.The display should now read "SWEETNER"
48.Press
49.When finished, press and release the right hidden switch, or press and release the "ENABLE BREW ON/OFF" switch to return to the main screen.
Page 15 | 41581.2 091609 |
|