START-UP CHECKLIST

(Remove and Store in Job File)

I. PRELIMINARY INFORMATION

MODEL NO.:
DATE:
SERIAL NO.:
TECHNICIAN:

II. PRE-START-UP (insert checkmark in box as each item is completed)

MVERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
MREMOVE ALL SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTALLATION INSTRUCTIONS
MVERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
MCHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
MCHECK THAT INDOOR AIR FILTER IS CLEAN AND IN PLACE
MVERIFY THAT UNIT INSTALLATION IS LEVEL
MCHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW
TIGHTNESS

III. START-UP

ELECTRICAL
SUPPLY VOLTAGE L1-L2 L2-L3 L3-L1
COMPRESSOR AMPS L1 L2 L3
INDOOR FAN AMPS
TEMPERATURES
OUTDOOR-AIR TEMPERATURE DB
RETURN-AIR TEMPERATURE DB WB
COOLING SUPPLY AIR
PRESSURES
REFRIGERANT SUCTION PSIG
REFRIGERANT DISCHARGE PSIG
MVERIFY THAT 3-PHASE SCROLL COMPRESSOR (50SS048,060; 50SX036-060 UNITS ONLY) IS ROTATING
IN CORRECT DIRECTION
MVERIFY REFRIGERANT CHARGE USING CHARGING CHARTS ON PAGES 28-33.
----------------------------------------------------------------------------------------
CUT ALONG DOTTED LINE
Copyright 1995 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, speciļ¬cations or designs without notice and without incurring obligations.
Book 1 4
Tab 1b 6b PC 111 Catalog No. 535-022 Printed in U.S.A. Form 50SS,SX-4SI Pg CL-1 5-95 Replaces: 50SS,SX-3SI