START-UP CHECKLIST
START-UP CHECKLIST
(Remove and Store in Job File)
I. PRELIMINARY INFORMATION
MODEL NO.: |
| SERIAL NO.: |
| ||
DATE: |
|
| TECHNICIAN: |
|
II.PRE-START-UP (insert checkmark in box as each item is completed)
j VERIFY THAT JOBSITE VOLTAGE AGREES WITH VOLTAGE LISTED ON RATING PLATE j VERIFY THAT ALL PACKAGING MATERIALS HAVE BEEN REMOVED FROM UNIT
j REMOVE ALL SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTALLATION INSTRUCTIONS j VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
j CHECK REFRIGERANT PIPING FOR INDICATIONS OF LEAKS; INVESTIGATE AND REPAIR IF NECESSARY j CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
j CHECK THAT RETURN (INDOOR) AIR FILTERS ARE CLEAN AND IN PLACE j VERIFY THAT UNIT INSTALLATION IS LEVEL
j CHECK FAN WHEELS AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW TIGHTNESS
j CHECK TO ENSURE THAT ELECTRICAL WIRING IS NOT IN CONTACT WITH REFRIGERANT LINES OR SHARP METAL EDGES
j CHECK PULLEY ALIGNMENT AND BELT TENSION PER INSTALLATION INSTRUCTIONS
III.START-UP
ELECTRICAL
SUPPLY VOLTAGE |
|
|
|
| |||
COMPRESSOR AMPS | L1 |
|
|
|
| L2 | L3 |
|
|
| |||||
L1 |
|
|
|
| L2 | L3 | |
|
|
| |||||
TEMPERATURES |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
| DB |
| ||||
|
|
| DB | WB | |||
|
|
| |||||
COOLING SUPPLY AIR |
|
|
|
|
| WB | |
|
|
| DB | ||||
|
|
|
|
|
|
|
|
PRESSURES (Cooling Mode) |
|
|
|
|
REFRIGERANT SUCTION |
| PSIG |
| F |
REFRIGERANT DISCHARGE |
| PSIG |
| F |
|
| |||
|
|
|
|
|
jVERIFY THAT
jVERIFY THAT
GENERAL
jSET ECONOMIZER MINIMUM VENT AND CHANGEOVER SETTINGS TO MATCH JOB REQUIREMENTS (IF EQUIPPED)