Chapter 2 Installing the Cisco Nexus 3000 Series Switches

Preparing for Installation

Se n d d o c u m e n t c o m m e n t s t o n ex u s 3 k - d o c f e e d b a ck @ c i sc o . c o m

Figure 2-1 Distinguishing Between Chassis with Forward and Reverse Airflow

1

No black stripe indicates forward airflow.

2

Black stripe indicates reverse airflow.

Chassis Weight

When lifting the switch chassis, follow these guidelines:

Disconnect all power and external cables before lifting the switch.

Ensure that your footing is solid and the weight of the switch is evenly distributed between your feet.

Lift the switch slowly, keeping your back straight. Lift with your legs, not with your back. Bend at the knees, not at the waist.

Installation Guidelines

When installing the Cisco Nexus 3000 Series switch, follow these guidelines:

Record the information listed in Appendix E, “Site Planning and Maintenance Records” as you install and configure the switch.

Ensure that there is adequate space around the switch to allow for servicing the switch and for adequate airflow (Appendix B, “Technical Specifications” lists the service and airflow requirements).

Ensure that the air-conditioning meets the heat dissipation requirements listed in Appendix B, “Technical Specifications.”

Ensure that the switch is going to be positioned so that it takes in air from a cold aisle and exhausts air to the hot aisle. If there is a black stripe across the front of these modules, they have forward airflow and must be positioned with the fan tray and power supplies in a cold aisle. If there is a black stripe across the front of these modules, they have reverse airflow and must be positioned with the port connections in a cold aisle.

Ensure that the cabinet or rack meets the requirements listed in Appendix A, “Cabinet and Rack Specifications.”

Note Jumper power cords are available for use in a cabinet. See the “Jumper Power Cord” section on page C-8.

Ensure that the chassis can be adequately grounded. If the switch is not mounted in a grounded rack, we recommend connecting both the system ground on the chassis and the power supply ground directly to an earth ground.

Cisco Nexus 3000 Series Hardware Installation Guide

 

OL-25338-04

2-3

 

 

 

Page 41