Chapter 4 Installation and Maintenance
Preparing to Install the SCE 2000 Platform
Cisco SCE 2000 4xGBE Installation and Configuration Guide
4-2 OL-7824-04
Figure 4-1: SCE 2000 Measurements
Table 4-1 SCE 2000 Dimensions
Dimension Measurement
Height 3.47 inches (9.5 cm)
Width 17.4 inches (4.43 cm)
Depth 18 inches (4.6 cm)
Weight 33 lb (15 kg)
Tools and Parts Required
The SCE 2000 chassis is fully assembled at the factory, including the application and software
packages. No assembly is required. However, you need the following tools and equipment to
install the SCE 2000 chassis and the rack-mount kit (if installing the SCE 2000 platform in a
rack), fan modules, and power supplies:
Number 1 and 2 Phillips screwdriver
1/4 inch flat-blade screwdriver
#¼” Hex Wrench
Screws compatible with your rack (for mounting the SCE 2000 to the rack)
12 AWG or 2.5-mm copper installation wire with hex or loop connectors for DC power
leads
Ring terminals must be UL approved and suitable for 12 AWG wire.
Level (optional)
Tape measure (optional)
Appropriate cables to connect the SCE 2000 to the network and console terminal
Rack-mounting kit (optional)
A new AC-input or DC-input power supply
A new fan module