Chapter 2 Introduction to the SCE Platform
SCE 2000 Installation Checklist
Cisco SCE 2000 4xGBE Installation and Configuration Guide
OL-7824-04 2-7
SCE 2000 Installation Checklist

To assist you with your installation and to provide a historical record of what was done by whom,

photocopy the following SCE 2000 Installation Checklist. Indicate when each procedure or

verification is completed. When the checklist is completed, place it in your site log along with the

other records for your new SCE 2000 platform.

Table 2-5 SCE 2000 Installation Checklist
Task Verified
By Date
Date SCE 2000 received
SCE 2000 and all accessories unpacked
Safety recommendations and guidelines reviewed
Topology verified: number of SCE 2000 platforms, number of links, and
whether inline or receive-only
Installation Checklist copied
Site log established and background information entered
Site power voltages verified
Site environmental specifications verified
Required passwords, IP addresses, device names, and so on, needed for
initial configuration available (refer to Setup Command Parameters (on
page 5-3))
Required tools available
Network connection equipment available
SCE 2000 mounted in rack (optional)
AC/DC power cables connected to AC/DC sources and SCE 2000 platform
Console port set for 9600 baud, 8 data bits, no parity, and 1 stop bit (9600
8N1)
ASCII terminal attached to console port
FE management ports are operational
GBE line and cascade ports operational
Network interface cables and devices connected
System power turned on
System boot complete (SYSTEM–UP LED is on)
Correct hardware configuration displayed after system banner appears