30
|Installation
6Connect the input and ground wires to the terminal block according to Figure 20 and Table 2.
Terminal Position
123
Figure 20. UPS Input Terminal Block
Table 2. UPS Wiring Specifications
Wire Function Terminal
Position UPS Wire Function Terminal Wire
Size Rating* Tightening Torque
Input 1Input Ground
5.26–16 mm2
(10–6 AWG) 2.49 Nm (22 lb in)
2L2/Neutral In
3L1 In
* Use a minimum:
S10 AWG for equipment grounding wire, 75_C copper wire minimum
S8 AWG for input line and neutral wires, 75_C copper wire minimum
7Replace the terminal block cover.8Continue to the following section, “UPS Initial Startup.”