5.9Checklist for Completed Installation

Site Preparation and Installation

5.9Checklist for Completed Installation

___ 1. Proper clearance for service access has been maintained around the equipment.

___ 2. Equipment is level and mounting fasteners are tight.

___ 3. Piping completed to refrigerant or coolant loop (if required). Refrigerant charge added (if required).

___ 4. Condensate pump installed (if required).

___ 5. Drain line(s) connected and checked for leaks.

___ 6. Water supply line connected to humidifier (if required). Route to allow air filter removal.

___ 7. Field provided drain pan with drain installed under all cooling units and ceiling-mounted water/glycol condensing units.

___ 8. Filter box installed.

___ 9. Ducting completed.

___ 10. Filter(s) installed in return air duct.

___ 11. Line voltage to power wiring matches equipment serial tag.

___ 12. Power wiring connections completed between disconnect switch, evaporator and condensing unit, including earth ground.

___ 13. Power line circuit breakers or fuses have proper ratings for equipment installed.

___ 14. Control wiring connections completed to evaporator and condensing unit (if required, including wiring to wall-mounted control panel and optional controls).

___ 15. Control panel DIP switches set based on customer requirements.

___ 16. All wiring connections are tight.

___ 17. Foreign materials have been removed from in and around all equipment installed (shipping materials, construction materials, tools, etc.)

___ 18. Fans and blowers rotate freely without unusual noise.

___ 19. Inspect all piping connections for leaks during initial operations. Correct as needed.

___ 20. Rubber band is removed from evaporator condensate pan float switch.