Installation is complete.
200A Current installation diagram
Callout | Component | Description |
|
|
|
1 | Power device | Any power component whose power current you want to measure |
2 | CH3, CH4, and CH5 CTs | Three separate current transducer channels to measure three current lines |
3 | Current lines | Three separate current lines measured by the CTs |
4 | Connection point | Low voltage wires connecting the CTs to the base station |
5 | Base station | Wirelessly transmits information to the Edge server |
6 | AC adapter | Plugs into a power source |
7 | Connector | Connects the base station to the AC adapter |
Installing the HP Energy Base Station
The HP Energy Base Station connects to the supplied ION energy meter sensor, and then measures and reports the energy usage of the monitored power source or location. Consult a professional electrician to install the ION power meter sensor to your power source.
Depending on the power configuration of your energy meter, the following KWH Base Stations are available:
•HP 208V/200A KWH Base Station
•HP 208V/600A KWH Base Station
•HP 480V/200A KWH Base Station
•HP 480V/600A KWH Base Station
The installation procedure is the same for all Energy base stations. To install a KWH base station:
NOTE: A licensed electrician must install the ION power meters to the designated locations of the data center.
(Optional) Sensor Base Stations 54