d.Insert the connector from the Door Position Base Station wire harness into the Door Position Base Station.

5.After all hardware is installed, power up the components ("Power up procedure" on page 70). Installation is complete.

Installing the HP Chilled Water Energy Base Station

The HP Chilled Water Energy Base Station connects to the housing box, which contains an ultrasonic probe sensor. The ultrasonic sensor measures and reports liquid flow through a chilled water pipe. Temperature sensors are installed on the supply and return of the same chilled water pipe to measure the rise of the temperature as chilled water enters and exits the data center room.

Consult a facility technician to install the ultrasonic probe sensor to your chilled water pipe. To install the Chilled Water Energy Base Station:

1.Choose a location for the housing box, relatively close to the chilled water pipes.

a.If a flat surface is available, remove the mounting tape liner, and secure the housing box to the surface.

(Optional) Sensor Base Stations 36