Field Calibration

Executing Field Calibration

The Field Calibration System is made up of the Field Calibration System Section and the Frame Section. It is necessary to assemble it when it is to be used for the first time or after it has been temporarily disassembled to move the Field Calibration System, etc. In addition, it is necessary to attach the Field Calibration System to the main unit in order to carry out field calibration.

Memo

VIVID 9i/VI-9i has been calibrated at 20ºC. The allowable operating environment is 10ºC to 40ºC, but we recommend that you execute Field Calibration or scan the objects in environments where ambient temperature is 20ºC (68ºF).

Assembling the Field Calibration System

[Procedure]

1 Install the Frame Section.

Install the Frame Section in a secure location with sufficient space.

Note

For the place that is necessary to install the Frame of the Field Calibration System, see page 33 of this instruction manual. A “Calibration Area” is also required for executing the calibration.

2 Adjust the Height of Rubber Feet to Stabilize the Frame Section.

The Frame of the Field Calibration System is designed to be used on a sufficiently wide, stable, flat sur- face. However, even if a sufficiently wide space is available, the surface may not be completely flat, resulting in one or more of the rubber feet of the frame not being in contact with the surface. To solve this problem, the feet have been equipped evenly with a mechanism to allow their height to be adjusted.

Memo

All 6 rubber feet have height adjustment mechanisms.

Note

Adjust a height of the rubber feet without any item on the frame during the procedure for setting up the frame of this system.

When transporting this system, set the rubber feet to their lowest height to avoid damage to the shopping box.

1Turn the lock nut counterclockwise to unlock the rubber foot block.

Unlock the rubber foot block by turning the lock nut counterclockwise.