Operation
3.2.9Start-Up Procedures Screen
From the SCC Master Menu, move the highlighted cursor to
This screen contains the steps you must follow to
Figure 42 SCC start- up procedures screen
SELECT : MASTER MENU
© 1989-2003
START-UP PROCEDURES
1.Wait approximately two (2) minutes before attempting any other action .
2.Select "SYSTEM CONFIGURATION" screen to verify that the correct model number is displayed.
3.Go to the modules(s) and follow the module "STARTUP PROCEDURES".
4.Select "MONITOR/MIMIC" screen, verify that the output voltages are at the proper nominal level and correct number of modules online is displayed.
5.If the bypass or static switch breakers are open, refer to
6.System is now ready to assume load. Select "LOAD TRANSFER PROCEDURES" screen for this procedure.
Prior to this procedure, supply power to the critical load through the bypass line.
Refer to 3.4.1 - SCC Start-Up Procedure for more details.
NOTE
If the system was shut down in response to an “Emergency Off” signal (typically because of a load fault), there may be alarm messages on the LCD screen that describe system conditions before (or at the time of) the shutdown. Some or all of the alarm conditions may have already been resolved. To clear these alarm messages, make sure the critical load is on bypass power and turn off the control power (see Figure 8 and Figure 9). Wait at least ten minutes for the control power circuitry to completely
From the module Master Menu, move the highlighted cursor to
This
55