6. Schedule setting6.1. Creation of projector group
Multiple projectors can be controlled and batched by sor ting groups.
Also,eachgroupcanseteachtimeofthepowersupplyON/OFFeveryday.
SincethescheduleofthepowersupplyON/OFFisperformedbyeachgr oup,theprojectorwhichyouliketo
operate at the same schedule should be integrated into the same group.
When Power ON and Power OFF are enabled, their time settings are indicated on the schedule lis t.
[Example] When setting the schedule for the group “group 1” to turn the power supply ON at 9:00 on Monday,
turning OFF at 17:00 on the same day, ON at 8:30 on Thursday, and OFF at 17:40 on Friday.
Group name
Day of the week
Time of power supply ON
Time of power supply OFF
When validating the setting,
putacheckmarkinthebox.
Schedule list
TimeofpowersupplyON/OFF
(1) Select “Add New Group” from “Configuration” of the menu bar.
• “AddNewGroup”windowisdisplayed.
(2) Input the group name to be created in the “Group N ame” column (within 16 characters in
one-byte alphanum eric symbol).
(3) Select the day of the week to be set for the time of the power s upply ON/OFF.
(4) Only when setting the time of the power supp ly ON, set the time in the “Power ON” column,
and put a check mark in the “E nable” box.
(5) Only when setting the time of power supply O FF, set the time in the “Power OFF” column,
and put a check mark in the “E nable” box.
(6) When there are more than one day of the week to be set for t he power supply ON/OFF
schedule, repeat the pr ocedure (3) to (5).