VENTING INSTALLATION

HBDV7 Series Direct Vent Gas Fireplace

Below Grade Installations

When it is not possible to meet the required vent terminal clearances of 12" above grade level, a snorkel kit is recom- mended. It allows installation depth down to 7" (178 mm) below grade level. The 7" (178 mm) is measured from the center of the horizontal vent pipe as it penetrates through the wall.

Ensure that sidewall venting clearances are observed. If venting system is installed below ground, we recom- mend a window well with adequate and proper drainage to be installed around the termination area.

If installing a snorkel, a minimum 24" vertical rise is neces- sary. The maximum horizontal run with the 24” vertical pipe

6.Slide the snorkel into the vent pipes and secure to the wall.

7.Level the soil so as to maintain a 4" clearance below snorkel. Figure 33

Do not back fill around snorkel.

A clearance of at least 4” must be maintained between the snorkel and the soil.

If the foundation is recessed, use recess brackets (not supplied) for securing lower portion of the snorkel. Fasten brackets to wall first, then secure to snorkel with self drill- ing #8 x 1/2 sheet metal screws. It will be necessary to extend vent pipes out as far as the protruding wall face. Figure 34

is 36". This measurement is taken from the collar of the fireplace (or transition elbow) to the face of the exterior wall. See the Sidewall Venting Graph for extended horizontal run if the vertical exceeds 24".

1.

Establish vent hole through the wall. Page 19, Figure

 

28

2.

Remove soil to a depth of approximately 16" below base

 

of snorkel. Install drain pipe. Install window well (not

 

supplied). Refill hole with 12" of coarse gravel leaving

 

a clearance of approximately 4" below snorkel. Figure

 

33

3.

Install vent system.

4.

Ensure a watertight seal is made around the vent pipe

 

coming through the wall.

5.

Apply high temperature sealant caulking (supplied)

 

around the 4" and 7" snorkel collars.

Foundation

Recess

Watertight Seal Around Pipe

Snorkel

Wall Screws

Sheet Metal

Screws

FP1966

 

Screws

 

Snorkel

Firestop

 

7”

Minimum 4”

Pipe

Clearance

 

 

Ground

24” (610 mm)

Window

Well

Minimum

 

 

Gravel

 

Drain

 

Foundation Wall

 

Figure 33 -

 

Below Grade Installation

 

BG402a

54D8000

 

Figure 34 -

Snorkel Installation, Recessed Foundation

VERTICAL THROUGH-THE-ROOF APPLICA- TION

his gas fireplace has been approved for:

Vertical installations up to 40’ (12 m) in height. Up to a 10’ (3 m) horizontal vent run can be installed within the vent system using a maximum of two 90° elbows. Figure 35

Up to two 45° elbows may be used within the horizontal run. For each 45° elbow used on the horizontal plane, the maximum horizontal length must be reduced by 18” (450 mm).

Example: Maximum horizontal length:

No elbows

= 10’ (3 m)

1 x 45° elbow

= 8.5’ (2.6 m)

2 x 45° elbows = 7’ (2.1 m)

A minimum of an 8’ (2.5 m) vertical rise is required.

Two sets of 45° elbow offsets may be used within the vertical sections. From 0 to a maximum of 8’ (2.5 m) of vent pipe can be used between elbows. Figure 35

21

Page 21
Image 21
Monessen Hearth HBDV400N/PSC7, HBDV300N/PV7 manual Below Grade Installations, Vertical THROUGH-THE-ROOF APPLICA- Tion