5-4 Power and Grounding Requirements
The input voltage for other communication equipment is typically
The input power is usually obtained from a centralized plant, which may be shared with other systems or dedicated to the equipment.
Power plant batteries provide backup power for the equipment in case of power outage. The backup time is typically 8 hours at the site with no engine- alternator or 3 hours at the site with an emergency
The grounding system of radio and transmission equipment typically conform to the Common Bonding Network (CBN) bonding topology.
Switching equipment conforms to the Isolated Bonding Network (IBN) grounding topology (typically,