Switchboard Case 9300 Series User’s Guide
Page 162 Chapter 7 - Hardware Reference
For the standard option, the meter is powered up when the voltage inputs
are applied in the next step.
9. Apply the current and voltage inputs:
For S1 style switchboard meters, insert the connection plug into the slot at
the bottom of the meter.
For FT21 style switchboard meters, push the shorting switches up.
10. Place the case cover into position and tighten the thumbscrew(s).
11. Perform basic setup and verify the meter’s operation: refer to the meter’s
Installation and Basic Setup Instructions manual for details.
Suggested Mounting Hole Dimensions
S1 Case HoleFT21 Case Hole
230mm(9.06")
246mm(9.69")
149mm(5.87")
141mm(5.55")
156mm(6.14")
146mm(5.75")
111mm(4.37")
210mm(8.27")