9300 Series User’s Guide Pre-configured Repor ts
Chapter 4 - Using ACCESS Software Page 95
Energy and Demand
This report is designed to generate and display details about energy consumption
and peak demand levels over a given time period. It uses a Time of Use Schedule
(TOU) to reference the metered data against an energy provider’s tariff schedule.
The first step in creating an Energy and Demand report is to preconfigure the TOU
schedule that will be applied to the metered data. If you do not require a time of
use schedule, you can create a mock schedule with only one time period defined.
Use the EgyDmd Log as a query item.
Load Profile
This report generates a graphical representation of demand, or load levels, over a
given time frame. The profile is a characterization of peak loads that can be used
to determine and limit demand peaks which could lead to financial penalties for
energy consumers, or could signal a need for additional generation or the
introduction of load control programs for energy suppliers.
The Load Profile report also uses the EgyDmd Log as a query item, but it does not
use a TOU schedule.
Power Quality
This report summarizes the number and severity of sags and swells over a given
time range, and graphically represents the waveform captures of each individual
event for further analysis.
The Power Quality report is slightly different than the other two report types -
mainly in its requirements for different data log sources. The Power Quality report
requires a combination of the Sag/Swell Log and Waveform Log.
EN50160
EN50160 is a general power quality standard used by energy suppliers and energy
consumers in European countries. The report is a summary of the multiple pass/
fail results of the evaluation methods outlined in the standard.
The following logs are used for the EN50160_General report:
EN50160 Vlt Dp1 to EN50160 Vlt Dp5
EN50160 Ovrvlt1 to EN50160 Ovrvlt3
EN50160 Frq/Mg, EN50160 Flicker, EN50160 Intrp, EN50160 Hrm Vlt, EN50160
Ihm Vlt, and EN50160 Vunbal
All fourteen of the above logs must be added to each EN50160_General report.
EN50160 MSignal is the log used for the EN50160_Mains_Signal report.
NOTE
The 73xx Series meters do not support EN50160 compliance. Although you see them as viable selections