7.Operate the chiller, looking for leaks and listening for unusual noises or vibrations that could indicate improper operation.

5-4 Remote Air-Cooled SCW Series Startup Checklist

;Check the shipping papers against the serial tag to be sure chiller size, type and voltage is correct for the process.

;Check the transformer primary voltage connections to be sure they are configured for the electrical power you are using.

;The voltage at the main power connection must read within plus or minus ten percent (±10%) of the voltage listed on the serial tag.

;Phase imbalance must be less than two percent (<2%).

;Electrical connections must conform to all applicable codes.

;Complete the chilled water TO PROCESS and FROM PROCESS connections.

;The optional or field installed chilled water supply and return valves must be open.

;Be sure the tank and chilled water circuit piping are filled with a water/glycol mixture. The water/glycol mix should provide freeze protection to 20°F below the leaving water temperature you’ve selected.

;The air cooled condenser should have an adequate supply of air for proper operation.

;Connect the main power to the unit and bump-start it to check for proper rotation direction. If the fans are operating backwards, reverse any two main power leads at the incoming terminal block.

;Remove all tools, foreign matter and debris from the pump tank reservoir and piping.

;Complete all piping leading to and from the pump tank. Observe all applicable codes.

;Complete all electrical wiring. Observe all applicable codes.

;Prepare all related equipment in the system for operation.

;Check for proper compressor rotation direction. To confirm proper rotation:

1. Connect a phase meter and phase incoming power ABC.

SCW Series Central Chilling Stations