All installations and services must be performed by qualified service personnel.
CEILING: Frame out area around where PVC pipe is to penetrate ceiling. Cut a
Figure 13.
K. CONDENSATE DRAIN LINE AND TRAP ASSEMBLY
1. Figure 14 illustrates the typical drain trap connection for a CMA/CMC furnace. (Trap will be installed at factory.) Connect condensate drain trap to building drain system.
2. An optional condensate neutralizer kit (P/n 320095) is available when gas furnace condensate needs to be neutralized (pH increased) prior to discharge into drain system.
3. An optional mini condensate pump (P/N 350224) is available. This pump will fit into the vestibule of the furnace.
Instructions will be included with pump if this option is utilized.
Figure 14.
30