ASSEMBLY
MOTOR SOLENOID VALVE MOUNTING
Install a motor solenoid valve to the bracket on main frame with the capscrews, star lockwasher flatwasher, lockwashers and hex nuts as shown in the parts section. Be sure that the pump and tank oil ports are pointing down. Be sure that the star and regular lockwashers are not on the same capscrew. Ground one of the red solenoid wires to the mounting bolts with the star lockwasher at this time.
CONTINUOUS DUTY SOLENOID SWITCH (OPTIONAL)
Mount the solenoid switch, drill holes to match, and 30 AMP breaker mounting tab, mount in dry and well protected area. Secure with 3/8” x 1” capscrews, lockwashers, and hex nuts.
A.) RED 6 GA. wire from terminal (D) to +12 volt battery post on starter solenoid. B.) RED 14 GA. wire from terminal (C) to +12 terminal on fuel pump.
C.) GREEN 14 GA. wire from terminal (B) to negative ground. D.) RED 8 GA. wire from terminal (A) to 30 AMP breaker.
E.) RED 14 GA. wire from terminal (A) to double switch box.
F.) RED 14 GA. wire from terminal (A) to temperature gauge. (optional) G.) RED 8 GA. wire from breaker to reverser switch terminal (2).
H)RED 8 GA. wire from terminal (1) to +12 volt terminal on cooler fan.
I).BLACK 8 GA. wire from terminal (3) to ground on cooler fan. J.) BLACK 8 GA. wire form terminal (4) to control panel ground.
Assembly Section