Connecting drain pipe
•Connect a hard socket (procured locally) to the hard socket of the attached supplied flexible hose.
•Connect a drain pipe (procured locally) to the connected hard socket.
REQUIREMENT
•Connect hard vinyl chloride pipes securely using an adhesive for vinyl chloride to avoid water leakage.
•It takes some time until the adhesive is dried and hardened (refer to the manual of the adhesive). Do not apply stress to the joint with the drain pipe during this time period.
Installation Manual
Pour water gradually so that water does not spread on the motor of the drain pump.
CAUTION
Pour water gently so that it does not spread around inside the indoor unit, which may cause a malfunction.
Heat exchanger
Float switch
connector (3P) (CN34: red)
Drain pan
Drain up
When a
•The height of the drain pipe must be 33.5" (850 mm) or less from the bottom of the ceiling.
•Take the drain pipe out of the drain pipe joint with the indoor unit in 11.8" (300 mm) or less, and bend up the pipe vertically.
•Immediately after the pipe is bent up vertically, lay the pipe making a
•Set downward grading immediately after raising up vertically.
|
|
|
|
|
|
| Rising up 26.0” (661 mm) or less |
| mm) or less |
|
|
|
|
|
|
|
| ||
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| up 33.5” (850 |
|
|
|
|
|
|
|
|
| |
| 11.8” (300 mm) | ||||||||
| or less | Rising | |||||||
|
|
|
|
|
|
|
|
|
Indoor unit
Underside of ceiling
Check the draining
In the test run, check that water drain is properly performed and water does not leak from the connecting part of the pipes.
Be sure to check draining also when installed in heating period.
Using a pitcher or hose, pour water (0.4 - 0.5 gal (1500 - 2000 cc)) into the discharge port before installation of the ceiling panel.
Tool for | Insert the hose end between the | |
heat exchanger and the drain pan, | ||
pouring | ||
and then bend the hose downward. | ||
water | ||
|
Bottle
Water (0.4 - 0.5 gal (1500 - 2000 cc))
• After the electric work has finished, pour water |
during COOL mode operation. |
• If the electric work has not yet finished, pull out the |
float switch connector (CN34 : Red) from the electric |
parts box, and check draining by plugging the single |
phase 208/230 V power to the terminal blocks L1 and |
L2. |
If doing so, the drain pump motor operates. |
• Test water drain while checking the operation sound |
of the drain pump motor. |
(If the operation sound changes from continuous |
sound to intermittent sound, water is normally |
drained.) |
After the check, the drain pump motor runs, |
connecting the float switch connector. |
(In case of check by pulling out the float switch |
connector, be sure to return the connector to the |
original position.) |
EN |
– 14 – |