Roberts Gorden POP-ECA/PGP-ECA 015 to 0100 CCH Wiring Diagram Gas Models 15-30 floor standing

Page 26

COMBAT® CABINET HEATERS INSTALLATION, COMMISSIONING, OPERATION AND SERVICE MANUAL

2.The control will then adjust the burner input continuously to attempt to maintain the temperature set on the control.

3.If the temperature continues to rise with the burner operating at minimum fire, the control will turn off the burner until the temperature falls again, and the burner will restart.

If a switch is required to turn on the main fan for ventilation, this must be voltage free, from external sources, and may be connected between terminals L1 & 1 for models 015 to 030 and terminals 2 & 1 for all other models.

9.3CCH Wiring Diagram Gas Models 15-30 (floor standing)

GAS BURNER 7 WAY PLUG

L1

L1

PACKAGED

BURNER

 

N

N

 

Blue

 

 

T1

T1

 

 

 

 

 

 

 

S3 T2

S3 T2

/ White

FAN / LIMIT STAT

 

Red / White

 

 

 

 

 

B4

B4

Red

FAN

 

 

 

 

Note: Remote fan control

 

 

 

LIMIT

 

 

 

 

carries full load of fan motor

 

 

 

 

7 amp inductive

 

 

 

 

 

TIME/TEMPERATURE

 

 

 

/ White

Red

CONTROLS

4

 

 

Red

 

 

 

 

 

 

 

3

 

Red / White

 

 

2

Red / White

10 A

 

 

 

 

 

 

FAN CONTROL

1

 

 

 

 

 

 

 

Brown

 

 

 

Red

 

 

 

L1

 

 

 

 

 

 

 

 

 

L2

 

 

MAIN

230 V 50 Hz

L3

 

 

FAN

 

 

MOTOR

1 PH SUPPLY

 

 

 

 

 

 

N

Blue

 

 

 

 

 

Blue

 

 

 

1 mm2 Ø Red Tri Rated Flex Cable

MAIN TERMINALS

IN CONTROL PANEL

NOTE:

Any of the original wire supplied with the heater must be replaced with wiring material having a temperature rating of at least 105°C and 600 V.

20

Image 26
Contents Supplier after leaving the building Improper installation, adjustment, alteration, serviceManual thoroughly before installing or servicing Immediately call your local gas Follow the gas supplier’sPage Roberts-Gordon LLC Page Table of Figures Page Product Approval National Standards and Applicable Codes Clearances to CombustiblesCorrosive Chemicals Location and Suspension All models Minimum Required Installation ClearancesCritical Considerations 3.1 Basic Information VentilationInstallation Clearances and Clearances to Combustibles All models Dimension Data PGP & POP Internal HeatersFront View all models Side View Models 015 Rear View Dimension Data PGP & POP External HeatersPGP & POP External Heaters Front View Side View Model 015/020/030 040 050 060/070/080 0100Outlet Spigot Dimensions Vertical and Horizontal Heaters Air Outlet Spigots top viewMax 45 mbar 18 in WG Model 015 020 030 040 050 060 070 080 0100Max 25 mbar 10 in WG Min 17 mbar 6.8 in WG Max 25 mbar 10 in WG Maximum Gross Heat InputKerosene Data Technical Data Ecoflam Oil-Fired Burners burner reference GLight Fuel Oil Gas Oil Data Heater Installation 5.1 General HandlingTypical Installation of a Oil-Fired Cabinet Heater Flue Installation 6.1 Flue Installation Flue TerminationSilicon Sealer Rain CollarJoint with high Building Ventilation AIR Supply 7.1 Air SupplyIsolated Equipment Rooms Distribution DuctingFuel Piping Gravity Feed Systems Fuel Oil Supply 8.2.1 Fuel Storage Tank Fuel Pipes 4 B. M. Oil LifterPressurised System Installation Duplex System Positioning Room Thermostats or Roberts-Gordon Control Remote ControlsBurner Controls Thermostat Remote Frost ThermostatCCH Wiring Diagram Gas Models 15-30 floor standing CCH Wiring Diagram Oil Models 15-30 floor standing CCH Wiring Diagram Gas Models 15-30 horizontal mounting GAS Burner 7-WAY PlugCCH Wiring Diagram Oil Models 15-30 horizontal mounting OIL Burner 6-WAY PlugCCH Wiring Diagram Gas Models 40-50 floor standing CCH Wiring Diagram Oil Models 40-50 floor standing Outputs Lockout Reset Signal From Burner RUN Signal CCH Wiring Diagram Oil Models 40-50 horizontal mounting CCH Wiring Diagram Gas Models 60-100 floor standing CCH Wiring Diagram Oil Models 60-100 floor standing CCH Wiring Diagram Gas Models 60-100 horizontal mounting CCH Wiring Diagram Oil Models 60-100 horizontal mounting Page Electrical Checks Polarity Test 1 ØLouvers Polarity Test 3 ØGas Supply Initial SettingCommissioning the Burner gas heaters Before Operating the HeaterSequence of Operation Control Gas-Fired HeatersDescription of Gas-Fired Heater Control Motor Starter and Thermal OverloadGas Train Circuit for Dungs Gas Valves all models Start Gas Valves Throughput AdjusterCombustion Testing all models Rate of OpeningHigh/Low and Modulating Burners Pressure SwitchComplete the Commissioning Commissioning the Burner Oil HeatersError Diagnosis Fault Display MessagesFault Display Fault ConditionsHigh/Low Operation Modulating OperationHeater Operation high/low or modulating Pull out for normal operation Press in for constant fanSimple Fault Finding burner faults Burner Lockout Reset ButtonSimple Fault Finding all models Simple Fault Finding oil fired heatersIf you smell gas Heat Exchanger Maintenance Burner Maintenance12.3 Fan/Motor Assembly Maintenance all models Servicing 12.1 Servicing InstructionsConversion Between Fuels 13.1 General Burner ConversionConduct Commissioning procedure as shown on Page 33, Section Conduct Commissioning procedure as shown on Page 33, Section Troubleshoot Ends Troubleshooting for Flame Supervision System Oil-Fired Gas-FiredTroubleshooting for Solenoid Valves Circuit Troubleshooting for Main Fan Circuit 1 ØTroubleshooting for Main Fan 3 Ø Conduct Commissioning procedure as on Page 33, SectionOverloads models 060 to Burner ComponentsContactor Control Circuit Fuse 10 or 5 A, 1-1/4 long sand filledRoberts Gordon Spare Parts List Description 015 020 030 040 050 060 070 080 0100Page Page Some objects can catch fire or explode when placed