WIRE CONNECTIONS

Recommended Torque Values

Torque all wire connections/fasteners to values recommended in Figure 10. Suitable for copper wire of 60°/75°C rating.

Figure 10 — Recommended Torque Values

CONNECTIONS:

Torque Value

 

 

In Main Distribution Panel:

 

Refer to panel manufacturer specs

 

 

 

In Disconnect Box:

 

 

 

240V AC Utility

5 in-lb

 

 

Engine Start

5 in-lb

 

 

Remote Status

5 in-lb

 

 

Generator

17 in-lb

 

 

Ground

40 in-lb

 

 

Circuit Breakers:

Refer to circuit breaker manufacturer specs

Generator AC Connection System

A single-phase, three-wire AC connection system is used in the Home Standby Generator.The stator assembly consists of a pair of stationary windings with two leads brought out of each winding.The junction of leads 22 and 33 forms the neutral lead. A complete schematic and wiring diagram can be found on pages 26-27.

NOTE: Neutral is not bonded to ground at generator.

Remote Diagnostic LED Plate

The light on the remote LED plate is referred to as the Diagnostic LED.The LED will stay lit indicating the generator is in ready mode and will turn on and off in a series of blinks if certain faults are detected in the Home Standby Generator.A mounting plate is supplied so that it can be installed at a convenient indoor location.The owner will use it to observe the status of the Home Standby Generator. Consult with the owner for a convenient location.

To install the remote diagnostic LED plate:

Mount installer-supplied electrical box to wall.

Using installer-supplied wire, connect the remote LED leads to the “Remote Status Light” in disconnect box.

NOTE: LED leads are polarity sensitive.

• Attach mounting plate to electrical box.

Refer to the section “Fault Detection System” on page 20 for operation.

BEFORE INITIAL START-UP

Engine Oil

This engine is shipped from the factory filled with the recommended oil. Before starting the engine, check oil level and ensure that engine is serviced as described in the engine owner’s manual.

Grounding the Generator

Installer-supplied stranded copper wire is connected to the disconnect box GND lug and routed through conduit to the Transfer Switch GND. Continue the wire through conduit to the main distribution panel ground bus.

Generator Control Circuit

Connection

Control circuit interconnections consist of "240V AC Utility" leads.These two leads must be routed in conduit. Control lead functions are briefly described as follows:

Leads deliver utility power to the generator’s circuit board, optional battery warmer and oil heater and charge the battery.

Using installer-supplied minimum 300V, 16 AWG stranded copper wire, connect control circuit terminals in the disconnect box to the Transfer Switch.

CAUTION

Any attempt to crank or start the engine before it has been properly serviced with the recommended oil will result in equipment failure.

Refer to engine manual for oil fill information.

Damage to equipment resulting from failure to follow this instruction will void warranty.

Oil Considerations

Your Home Standby Generator is equipped with an engine that has been pre-run at the factory and does not require the traditional “break-in” procedure.

The generator is filled with synthetic oil (API SJ/CF 5W- 30W).This allows for generator operation in the widest range of temperature and climate conditions.

NOTE: The use of synthetic oil DOES NOT alter the required oil change intervals described in the engine owner’s manual.

16

Image 16
Contents Installation Start-Up Table of Contents Do not dispose of battery in a fire Important Safety InstructionsOperate generator only outdoors Amp fuse Before working on the equipment Installer Responsibilities Installation AssistanceSave These Customer Instructions Responsibilities IntroductionKnow Your Home Standby Generator BatteryOil Fill Know Your Control Panel AUTO/OFF/MANUALInstallation Procedures Owner OrientationLifting the Generator Shipment ContentsHome Standby Generator Location Essential Circuit Selection Essential CircuitsDevice Running Watts Removable Roof and Access Door Fuel Inlet DimensionsDisconnect Box Mounting Guidelines Gaseous Fuel System Fuel Consumption From FuelTo Home Standby LoadFuel Pipe Sizing 10ft 15ft 20ft 30ft 40ft 50ft 60ft 70ft 80ft 90ft 100ftPhysical Properties Propane Natural Gas Fuel Comparison ChartWithdrawal Rate 32F 20F 10F 30F 40F Wire Connections Before Initial START-UPBattery Connection Charging the BatteryServicing the Battery Fuel Supply SystemAutomatic Operation Sequence Fuel System SelectionInitial START-UP no Load Installation Inspection Setting Exercise TimerTo perform the Set Exercise procedure Specifications Fault Detection SystemAutomatic Operation Servicing the SystemNumber of LED Flashes Fault Description Reset Fault Detection SystemNo LED Discharged Battery Engine Fail To StartGenerator Maintenance Changing Engine Oil and FilterChanging Oil Changing Oil FilterWhen Calling the Factory To Clean the GeneratorStorage Troubleshooting Problem Cause CorrectionBriggs & Stratton Power Products Home Standby Generator Schematic Wiring Diagram Exploded View Main Unit Parts List Main Unit Optional Accessories Not IllustratedDescription Items Not IllustratedExploded View Enclosure Parts List Enclosure Exploded View Control Panel Parts List Control Panel Exploded View and Parts List Alternator HARNESS,Wire DC ChargeADAPTER, Mounting,Alternator SCREW, M5 .8 x 10 TaptiteConsumer Use Years Years or YearManual de Instalación,Arranque y Propietario Tabla DE ContenidoSensor de Excitación de Tensión de la Compañía Advertencia PeligroPrecaución Los generadores producen un voltaje muy poderosoConserve Estas Instrucciones IntroducciónResponsabilidades DEL Cliente Responsabilidades DEL InstaladorConozca SU Generador DE Reserva Etiqueta del Motor Tapón de Llenado y VarillaDe Nivel de Aceite Tapón de Llenado y Varilla de Nivel de Aceite PermiteConozca EL Panel DE Control Fusible deDisyuntor Interruptor Fusible de 15 Amperios Protege los circuitos de control deOrientación Para EL Propietario Procedimientos DE InstalaciónElevación del Generador Contenido de la CajaUbicación del Generador de Reserva Selección de los Circuitos Fundamentales Circuitos FundamentalesDispositivo Vatiaje de Directrices de Montaje del Cuadro de Desconexión Dimensiones de la Entrada de CombustibleTecho y Puerta de Acceso Desmontables Sistema DE Combustible Gaseoso Advertencia El generador de reserva viene preparado de fábrica paraConsumo de Combustible Gas Natural Vapor de PLGas Natural peso específico = Dimensiones de la Cañería de CombustiblePropano Líquido PL peso específico = Propiedades físicas Propano Gas natural Cuadro de Comparación de CombustiblesTasa de consumo 32F 20F 10F 30F 40F Conexiones DE Cables Antes DEL Arranque InicialConexión de la Batería Sistema de Suministro de CombustibleCargar la Batería Servicio la BateríaArranque Inicial SIN Carga Selección DEL Sistema DE CombustibleSecuencia DE Operación Automática Inspección Posterior a LA Instalación Ajuste DEL Temporizador DE EjercicioTemporizador de enfriamiento del motor Especificaciones Operación AutomáticaSistema DE Detección DE FallasCantidad de Destellos del LED Descripción de la Falla Restablecimiento del Sistema de Detección de FallasNo se Enciende el LED Batería Descargada Baja Presión de AceiteMantenimiento DEL Generador Cambio del Aceite del Motor y del FiltroCambio del Filtro de Aceite Cambio del AceitePara Limpiar el Generador AlmacenamientoSi Llama a la Fábrica Reparacion DE Averias Garantía Limitada Manuel dInstallation, Démarrage et Utilisateur Table DES MatièresFonctionnement Automatique Entretien DE LA GénératriceAvertissement NE touchez PAS les fils dénudés ou les boîtiers Responsabilités DE Linstallateur Aide À LinstallationConservez CES Instructions IntroductionFAMILIARISEZ-VOUS Avec Votre Génératrice D’ÉTAT D’ATTENTE Filtre à Air Et Jauge dHuile Filtre à lHuile15 Ampères FAMILIARISEZ-VOUS Avec LE Tableau DE CommandeDisjoncteur Interrupteur Procédures Dinstallation Conseils AU PropriétaireEmplacement du Génératrice d’état d’Attente Directives Générales Concernant lEmplacementContenu de la Boîte Soulèvement de la GénératriceSélection des Circuits Essentiels Circuits EssentielsAppareil Watts Directives dAssemblage du Boîtier de Débranchement Dimensions de lOrifice dAdmission du CombustibleToit Amovible et Porte dAccès LE Système DE Combustible Gazeux Avertissement Le génératrice d’état d’attente a été réglé en usine pourConsommation de Combustible Gas Naturel Vapeur PLGaz Naturel densité = 0,65 Grosseur du Tuyau de CombustibleGaz de Pétrole Liquéfié GPL densité = 1,50 Charte de Comparaison des Combustibles Propriétés physiques Propane Gaz naturelRaccords DE Fils Avant LE Démarrage InitialBranchement de la Batterie Système dAlimentation en CombustibleRechargez la Batterie Entretien de la BatterieCapteur de Prise en Charge de la Tension de Service Sélection DU Système DE CombustibleDémarrage Initial Sans Séquence DE Fonctionnement AutomatiqueVérification Installation Warranty Registration Box Milwaukee,WisconsinRéglage DE LA Minuterie DU Cycle Dexercice Minuterie de Refroidissement du MoteurCaractéristiques Fonctionnement AutomatiqueSystème DE Détection DES Pannes Entretien du SystèmeClignotements Du Voyant Réarmement du Système de Détection des PannesAucun DEL Batterie déchargée Faible Pression dHuileEntretien DU Générateur Changement dHuile à Moteur et de FiltreChangement du filtre à huile Vidange de lHuilePour Nettoyer le Générateur RemisageCommunications avec le Fabricant Dépannage Remarques Garantie Limitée